Mumbai Metro Line 2A (DAHISAR - D.N. NAGAR)

Mumbai Metro Line 2A (DAHISAR - D.N. NAGAR)

  • Metro Line 2A from Dahisar to D N Nagar is 18.589 km. long elevated corridor with 17 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Lines 2B (D N Nagar to Mandale) & 7 (Andheri (E) to Dahisar (E)) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Dahisar and D N Nagar.
  • It shall provide connectivity between the Western, Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the commercial and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Project Features

 
Length 18.589 km (Elevated)
Stations 17 Nos. (All Elevated)
  1. Dahisar, 2. Anand Nagar, 3. Rushi Sankul, 4. I.C. Colony, 5. Eksar, 6. Don Bosco, 7. Shimpoli, 8. Mahavir Nagar, 9. Kamraj Nagar, 10. Charkop, 11. Malad Metro, 12. Kasturi Park, 13. Bangur Nagar, 14. Goregaon Metro, 15. Adarsha Nagar, 16. Shastri Nagar, 17. D.N. Nagar
Elevated / Underground Elevated along Link Road
Interchange stations for Metro
  1. D. N. Nagar (Line 1 : Ghatkopar - Versova)
  2. Dahisar (Line 7 : (Andheri (E) - Dahisar (E) corridor)
Project completion cost Rs. 6,410 Cr. ((including state taxes and 7.5% p.a escalation & IDC)
Ridership :  
2021 Daily Ridership - 4.07 Lakhs (PHPD 11560)
2031 Daily Ridership - 6.09 Lakhs (PHPD 15565)
Rolling Stock
Width : 3.20 m
Height : 3.90 m
Length : 21.84 m
 
Axle load - 17 tonnes
Seating Arragement - Longitudinal
Capacity
6 coach train - 1756 persons
8 coach train - 2244 persons

 

Present Status

Updates as on 9th January 2018
Sr. No. Name of Work Status
1 Soil Investigation Works 94% of the soil investigation work for Pier foundation is completed
2 Barricading Works 89% barricading work is completed
3 Piling Works 61% (2797 out of 4576 nos. completed)
4 Pile Cap Works 43% (406 out of 945 nos. completed)
5 Pier Works 31% completed (300 out of 957 nos. are cast)
6 Pier Cap Works 236 are cast (28%) and 199 (24%) are erected out of 827 nos.
7 U Girder Works 343 are cast (24%) and 146 are erected (10%) out of 1430 nos.
8 Station Work Work in progress in all the 17 stations
 