Mumbai Metro Line 2B (D.N. NAGAR - MANDALE)

Mumbai Metro Line 2B (D.N. NAGAR - MANDALE)

  • Metro Line 2B from D N Nagar to Mandale is 23.643 km. long elevated corridor with 20 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Eastern Express Highway, Western Railway, Central Railway, Mono Rail, Metro Line 1 (Ghatkopar to Versova) and Metro Line 2A (Dahisar to D N Nagar), Metro Line 4 (Wadala to Kasarvadavali) & Metro Line 3 (Colaba to SEEPZ) under implementation.
  • It shall provide connectivity between the Eastern & Western Suburban Mumbai.
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • Dedicated Depot is planned at Mandale in up to an extent of 22 Ha. land area.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Project Features

 

 

Length 23.643 km (Elevated)
Line Color Yellow
Stations 20 Nos. (All Elevated)
  1. ESIC Nagar, 2. Prem Nagar, 3. Indira Nagar, 4. Nanavati Hospital, 5. Khira Nagar, 6. Saraswat Nagar, 7. National College, 8. Bandra Metro, 9. Income Tax office, 10. ILFS, 11. MTNL Metro, 12. SG Barve Marg, 13. Kurla (E), 14. EEH, 15. Chembur, 16. Diamond Garden, 17. Shivaji Chowk, 18. BSNL Metro, 19. Mankhurd, 20. Mandale Metro.
Elevated / Underground Fully Elevated
Depot Mandale (31.4 Ha)
Interchange stations for Metro
  1. D. N. Nagar (Line 1)
  2. Bandra (Suburban)
  3. ITO junction (Line 3)
  4. Kurla East (Suburban & Line 4)
  5. Chembur (Monorail)
  6. Mankhurd (Suburban, CST-Panvel fast corridor
  7. Mumbai-Navi Mumbai Airport fast corridor)
Project completion cost Rs. 10,986 Cr. (incl state taxes, 7.5% p.a escalation and IDC)
Ridership for Total length :  
2031 Daily Ridership - 10.5 Lakhs (PHPD 38509)

 

Present Status

Updates as on 5th Sept 2022
 
Sr. No. Name of Work Status
1 Soil Investigation Works 90.57% completed.
2 Utility Works 65.21% completed.
3 Pile Group Works 49.46% completed.
4 Pile Cap Works 37.28% completed.
5 Pier Works 33.31% completed.
6 Pier Cap Works

Casting - 24.36% completed.
Erection -21.27 %completed.

7 U Girder Works

Casting - 34.48% completed.
Erection - 20.69% completed.

8 Mandale Depot works 40.06% completed.
 