Transport
- Multimodal Corridor from Virar to Alibaug
- Metro Line - 1
- Metro Line - 2A
- Metro Line - 2B
- Metro Line - 4
- Metro Line - 5
- Metro Line 6
- Metro Line - 7
- Metro Line - 9
- Mumbai Monorail
- Mumbai Trans Harbour Link
- Mumbai Trans Harbor Link – Metro Link
- Mumbai Urban Transport Project
-
Mumbai Urban Transport
Project - || - National Mass Transit Training and Research Institute
- Comprehensive Transport Study
- InterState Bus Terminal
- UMMTA
Infrastructure
Environment
Innovations
International Financial Services Centre
eGovernance
Development Finance
Social Development / R&R
Additional
Mumbai Metro Line 2B (D.N. NAGAR - MANDALE)
- Metro Line 2B from D N Nagar to Mandale is 23.643 km. long elevated corridor with 20 stations.
- It shall provide interconnectivity among the existing Western Express Highway, Eastern Express Highway, Western Railway, Central Railway, Mono Rail, Metro Line 1 (Ghatkopar to Versova) and Metro Line 2A (Dahisar to D N Nagar), Metro Line 4 (Wadala to Kasarvadavali) & Metro Line 3 (Colaba to SEEPZ) under implementation.
- It shall provide connectivity between the Eastern & Western Suburban Mumbai.
- It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
- Dedicated Depot is planned at Mandale in up to an extent of 22 Ha. land area.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Project Features
Length | 23.643 km (Elevated) |
Line Color | Yellow |
Stations | 20 Nos. (All Elevated) |
1. ESIC Nagar, 2. Prem Nagar, 3. Indira Nagar, 4. Nanavati Hospital, 5. Khira Nagar, 6. Saraswat Nagar, 7. National College, 8. Bandra Metro, 9. Income Tax office, 10. ILFS, 11. MTNL Metro, 12. SG Barve Marg, 13. Kurla (E), 14. EEH, 15. Chembur, 16. Diamond Garden, 17. Shivaji Chowk, 18. BSNL Metro, 19. Mankhurd, 20. Mandale Metro. | |
Elevated / Underground | Fully Elevated |
Depot | Mandale (31.4 Ha) |
Interchange stations for Metro |
|
Project completion cost | Rs. 10,986 Cr. (incl state taxes, 7.5% p.a escalation and IDC) |
Ridership for Total length : | |
2031 | Daily Ridership - 10.5 Lakhs (PHPD 38509) |
Present Status
Updates as on 5th Sept 2022
Sr. No. | Name of Work | Status |
---|---|---|
1 | Soil Investigation Works | 90.57% completed. |
2 | Utility Works | 65.21% completed. |
3 | Pile Group Works | 49.46% completed. |
4 | Pile Cap Works | 37.28% completed. |
5 | Pier Works | 33.31% completed. |
6 | Pier Cap Works | Casting - 24.36% completed. |
7 | U Girder Works | Casting - 34.48% completed. |
8 | Mandale Depot works | 40.06% completed. |