Transport
- Multimodal Corridor from Virar to Alibaug
- Metro Line - 1
- Metro Line - 2A
- Metro Line - 2B
- Metro Line - 4
- Metro Line - 5
- Metro Line 6
- Metro Line - 7
- Metro Line - 9
- Mumbai Monorail
- Mumbai Trans Harbour Link
- Mumbai Trans Harbor Link – Metro Link
- Mumbai Urban Transport Project
-
Mumbai Urban Transport
Project - || - National Mass Transit Training and Research Institute
- Comprehensive Transport Study
- InterState Bus Terminal
- UMMTA
Infrastructure
Environment
Innovations
International Financial Services Centre
eGovernance
Development Finance
Social Development / R&R
Additional
Metro Line - 5 (Thane Bhiwandi Kalyan)
- Metro Line 5 from Thane to Bhiwandi to Kalyan is 24.90 km. long elevated corridor with 15 stations.
- It will provide interconnectivity among the ongoing Metro Line 4 (Wadala to Kasarvadavli) and the proposed Metro Line 12 (Kalyan to Taloja), and with the existing Central Railway.
- It will provide rail based access to the commercial, Govt. bodies and geographical landmarks in Thane, Bhiwandi and Kalayan.
- It will reduce the current travel time by anything between 50% and 75%
Project Features
Length | 24.9 km (Elevated) |
Stations | 15 Nos. (All elevated) |
1. Balkum Naka, 2. Kasheli, 3. Kalher, 4. Purna, 5. Anjurphata, 6. Dhamankar Naka, 7. Bhiwandi, 8. Gopal Nagar, 9. Temghar, 10. Rajnouli, 11. Gove Gaon, 12. Kon Gaon, 13. Lal Chowki, 14. Kalyan Station, 15. Kalyan APMC. | |
Elevated / Underground | Fully Elevated |
Project base cost | Rs. 8416.51 Cr. (including Taxes and Duties) |
Ridership : | |
2031 | Daily Ridership –3.025 Lakhs (PHPDT- 26143) |
Rolling Stock | Width : 3.20 m Height : 3.90 m Length : 21.84 m |
Capacity | System designed for 6 coach train : 1756 persons |
Present Status
Present Status (Updated as on 1st Jan 2021)
Sr. No. | Details | Status in % |
---|---|---|
Phase 1 – (Thane to Bhiwandi) | ||
1 | Soil Investigation Works | 82% of the soil investigation work for Pier foundation is completed. |
2 | Utility Works | 68% completed |
3 | Piling Works | 59% completed. |
4 | Pile Cap Works | 41% completed. |
5 | Pier Works | 25% completed. |
6 | Pier Cap Works | 7% completed. |
7 | U Girder | 1% completed. |
Phase 2 – (Bhiwandi to Kalyan) | M/s Delhi Metro Rail Corporation is appointed to finalize the alignment and to prepare the revise DPR |
Key Map
Photo Status
Casting Yard Progress Photographs
Site Work