Mumbai Metro Line 7 (ANDHERI EAST - DAHISAR EAST)

Mumbai Metro Line 7 (ANDHERI EAST - DAHISAR EAST)

  • Metro Line 7 from Andheri (E) to Dahisar (E) is 16.475 km. long elevated corridor with 13 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, Metro Line 1 (Ghatkopar to Versova), the ongoing Metro Line 2A (Dahisar to D N Nagar) and the proposed Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall facilitate smooth and efficient interchange with the suburban rail system and MRT system at Andheri, JVLR and Dahisar.
  • It shall provide connectivity between the Central Mumbai and the Northern suburban Mumbai.
  • It shall provide rail based access to the Mumbai International Airport (CSIA), SEEPZ, National Park and other commercial and geographical landmarks.
  • Dedicated Depot is planned at Dahisar in an extent of 15 Ha.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Project Features

 
Length 16.475 km (Elevated)
Stations 13 Nos. (All elevated)
  1. Andheri Metro (E), 2. Shankarwadi, 3. JVLR Jn., 4. Mahanand, 5. Aarey, 6. Pathan Wadi, 7. Pushpa Park, 8. Bandongri, 9. Mahindra & Mahindra, 10. Magathane, 11. Devipada, 12. National Park, 13. Ovaripada
Elevated / Underground Elevated along Western Express way
Interchange stations for Metro
  1. At Andheri (Line 1 : WEH Station of Ghatkopar - Versova)
  2. At Dahisar (Line 2A : Dahisar - D N Nagar)
  3. At JVLR Jn. (Line 6 : Swami Samarth Nagar - Kanjurmarg)
Project completion cost Rs. 6208 Cr. (including state taxes and 7.5% p.a escalation)
Ridership :  
2019 Daily Ridership - 4.73 Lakhs (PHPDT- 15602)
2021 Daily Ridership - 5.28 Lakhs (PHPDT- 18086)
2031 Daily Ridership - 6.68 Lakhs (PHPDT- 18584)
Rolling Stock
Width : 3.20 m
Height : 3.90 m
Length : 21.84 m
 
Axle load - 17 tonnes
Seating Arragement - Longitudinal
Capacity
6 coach train - 1756 persons
8 coach train - 2244 persons

 

Present Status

Updates as on 16th July 2018
Sr. No. Name of Work Status
1 Soil Investigation Works 98% of the soil investigation work for Pier foundation is completed
2 Utility Works 93% work is completed
3 Piling Works 89% (2867 out of 3204) of Piling work for 561 out of 709 no. of foundations completed
4 Pile Cap Works 69% completed (461 out of 709)
5 Pier Works 51% completed (308 out of 709)
6 Pier Cap Works 307 no. are cast (46%) and 262 nos. are erected (39%)
7 U Girder Works 478 no. are cast (40%) and 320 nos. are erected (27%)
8 Station Work Work is in progress at all the 13 stations
 