The work of development of 403 MLD capacity Surya Regional Water Supply Scheme in undertaken to provide bulk water supply to Mira-Bhayander Municipal Corporation (MBMC) and Vasai Virar City Municipal Corporation (VVCMC) including Rental Housing Complexes and 27 villages located in the Western Sub Region of MMR.

Project Features

  • Name of Project - 403 MLD capacity Surya Regional Water Supply Scheme.
  • Source of Raw water - Surya Dam of GoM, at village Dhamani, Tal : Jawhar.
  • Major components of works are :
  1. Raw Water Pumping Station with 132 kv Sub Station.
  2. Water Treatment Plant
  3. Chlorination Plant
  4. Pure Water Pumping Station with 132 kv Sub Station
  5. Break Pressure Tower
  6. Gravity Transmission Main of 2235/1829 mm dia for 85 km length
  7. Master Balancing Reservoirs - 2 Nos (45 ML-MBMC & 38 ML-VVCMC)
  • An estimated cost of the Project - Rs. 1325.78 Cr.

Details of Project

As per the layout of Scheme, Raw Water is to be lifted from Kawadas pick-up weir located at the down stream of Surya Dam and proposed to be treated at Water Treatment Plant at Surya Nagar. The treated water will be transmitted through gravity main to be laid along the State Highway no.30 and National highway No.8 up to Mater Balancing Reservoir (MBR) of VVCMC at KashidKopar and also MBR of MBMC at Ghodbander. The further distribution is to be managed by the concerned local bodies through their distribution systems.

Present Status

Updates as on 17th May 2019

Current Status of Project

Sr. No. Item of Work Sub-Component Current Status
1 Survey,Investigation including Geotechnical Investigation & Design. Topographical alignment survey & block contour survey 100 % Completed.
Raw Water Analysis 100% Completed.
Intake 100% Completed.
Water Treatment plant & Break Pressure Tank 100% Completed.
Pipe line including Soil resistivity Survey 85% Completed.s
Mendhvakhind Tunnel 100% Completed.
Tungareshwar WLS Tunnel 100% Completed.
Kaman Creek Micro Tunnel 100% Completed.
Vasai Creek Micro Tunnel 100% Completed.
Survey & Geotechnical investigation at Ghodbundar road crossing 100% Completed.
2 Measures of Environmental Management Plan & Permissions. Environment Monitoring Permissions 95% Completed.
Forest Land Clearance 95% Completed.
3 Gravity Main From BPT To Kashidkopar Junction.(Total Length:55.520 Km) Manufacturing of 2235X12.5 mm dia. M.S. pipe 77% Completed.
Laying work 5% Completed.
4 Gravity Main From Kashidkopar Junction To Chene MBR(Total Length:20.845 Km) Manufacturing of 1829X12.5 mm dia. M.S. pipe 85% Completed
5 Mendhvankhind Tunnel Shaft construction work 17% Completed.
 