inner-banner

Metro Line - 9 & 7A

Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)

  • Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
 
Length 13.581 km
Stations 10 Nos.
 

Dahisar (E) to Mira-Bhayander ( All Elevated)

1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium

Andheri (E) to CSIA extension

1. Airport Colony (elevated) and 2. CSIA (underground)

Elevated / Underground 11.386 km elevated and 2.195 km underground
Project base cost Rs. 6607 Crore (including state taxes and 7.5% p.a escalation)
Ridership :
2021 Daily Ridership - 8.47 Lakh (PHPDT- 24585)
2031 Daily Ridership – 11.12 Lakh (PHPDT- 30389)
Rolling Stock

Width : 3.20 m

Height : 3.90 m

Length : 21.84 m

Capacity

8 coach train : 2352 persons

Updates as on 12th February 2024

Sr. No. Name of Work Status in %
Elevated Viaduct
1. Working Pile 83% Completed
2.        Pile cap 79% Completed
3.        Pier 78% Completed
4.        Pier Cap Casting 74% Completed
5.        Pier Cap Erection 73% Completed
6.        U-Girder Casting 71% Completed
7.        Portal Beam Casting 76% Completed
8.        Portal beam Erection 71% Completed
9.        I-Girder Casting 66% Completed
10.    I-Girder Erection 42% Completed
11.    Deck Slab Casting 21% Completed
12.    Parapet Casting 32% Completed
13.    Parapet Erection 07% Completed
Elevated Station
14.    Working Pile 100% Completed
15.    Pile cap 100% Completed
16.    Pier (CL to PL) 97% Completed
17.    Pier – DHS Station (GL to PL) 100% Completed
18.    Hammer Head 97% Completed
19.    Concourse Pier Arm Erection 92% Completed
20.    Platform Pier arm Erection 95% Completed
21.    Portal beam Erection (Dahisar Station) 67% Completed
22.    U-Girder Casting 87% Completed
23.    U-Girder Erection 77% Completed
24.    L-Girder Erection 64% Completed
25.    T-Girder Erection 77% Completed
Flyover
26.    Pile cap 50% Completed
27.    Pier 87% Completed
28.    Hammer Head 89% Completed
29.    Abutment Pile Cap 75% Completed
30.    Dirt Wall 58% Completed
31.    Flyover Pier Cap Erection 95% Completed
32.    I-Girder Erection 74% Completed
33.    Deck Slab Casting 42% Completed
Entry Exit
34.   Working Pile 33% Completed
35.   Pile cap 20% Completed
36.   Columns 17% Completed
LINE 7A
Elevated Viaduct
1.        Working Pile 100% Completed
2.        Pier Cap Casting 91% Completed
3.        Pier Cap Erection 82% Completed
4.        U-Girder Casting 85% Completed
5.        U-Girder Erection 53% Completed
Elevated Station
1.        Working Pile 100% Completed
2.        Entry Exit-2 Piling 89% Completed
3.        Monolithic Pier 100% Completed
4.        Portal Pier (Up to PL) 100% Completed
5.        Pier Cap Casting 67% Completed
6.        Pier Cap Erection 33% Completed
7.        Portal Beam Casting at PL (Cast in Situ) 67% Completed
8.        U-Girder Casting 09% Completed
ELEVATED RAMP
1.           Elevated Ramp 15% Completed
CUT & COVER AND UG RAMP
1 Cut & Cover  
a.    Micro Pile 66% Completed
b.    Excavation 20% Completed
c.    Anchor Drilling & Grouting 15% Completed
d.    Waler Erection 05% Completed
2 UG Ramp  
a.         Capping Beam 69% Completed
b.        Excavation 70% Completed
UG CSMIA Station
1.        Excavation (m3) 77% Completed
2.        Anchor installation & grouting 76% Completed
3.        Waler Erection 68% Completed
4.        Anchor Stressing 71% Completed
Tunnel
1.        Tunnel Ring Segment Casting 66% Completed
2.        TBM-1 Main Drive (Down Line) 21% Completed
3.        TBM-2 Main Drive (Up Line) 07% Completed
Key Map