Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)
- Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
- It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
- It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
- It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Length | 13.581 km |
Stations | 10 Nos. |
Dahisar (E) to Mira-Bhayander ( All Elevated) 1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium Andheri (E) to CSIA extension 1. Airport Colony (elevated) and 2. CSIA (underground) |
|
Elevated / Underground | 11.386 km elevated and 2.195 km underground |
Project base cost | Rs. 6607 Crore (including state taxes and 7.5% p.a escalation) |
Ridership : | |
2021 | Daily Ridership - 8.47 Lakh (PHPDT- 24585) |
2031 | Daily Ridership – 11.12 Lakh (PHPDT- 30389) |
Rolling Stock |
Width : 3.20 m Height : 3.90 m Length : 21.84 m |
Capacity |
8 coach train : 2352 persons |
Updates as on 12th February 2024
Sr. No. | Name of Work | Status in % |
---|---|---|
Elevated Viaduct | ||
1. | Working Pile | 83% Completed |
2. | Pile cap | 79% Completed |
3. | Pier | 78% Completed |
4. | Pier Cap Casting | 74% Completed |
5. | Pier Cap Erection | 73% Completed |
6. | U-Girder Casting | 71% Completed |
7. | Portal Beam Casting | 76% Completed |
8. | Portal beam Erection | 71% Completed |
9. | I-Girder Casting | 66% Completed |
10. | I-Girder Erection | 42% Completed |
11. | Deck Slab Casting | 21% Completed |
12. | Parapet Casting | 32% Completed |
13. | Parapet Erection | 07% Completed |
Elevated Station | ||
14. | Working Pile | 100% Completed |
15. | Pile cap | 100% Completed |
16. | Pier (CL to PL) | 97% Completed |
17. | Pier – DHS Station (GL to PL) | 100% Completed |
18. | Hammer Head | 97% Completed |
19. | Concourse Pier Arm Erection | 92% Completed |
20. | Platform Pier arm Erection | 95% Completed |
21. | Portal beam Erection (Dahisar Station) | 67% Completed |
22. | U-Girder Casting | 87% Completed |
23. | U-Girder Erection | 77% Completed |
24. | L-Girder Erection | 64% Completed |
25. | T-Girder Erection | 77% Completed |
Flyover | ||
26. | Pile cap | 50% Completed |
27. | Pier | 87% Completed |
28. | Hammer Head | 89% Completed |
29. | Abutment Pile Cap | 75% Completed |
30. | Dirt Wall | 58% Completed |
31. | Flyover Pier Cap Erection | 95% Completed |
32. | I-Girder Erection | 74% Completed |
33. | Deck Slab Casting | 42% Completed |
Entry Exit | ||
34. | Working Pile | 33% Completed |
35. | Pile cap | 20% Completed |
36. | Columns | 17% Completed |
LINE 7A | ||
Elevated Viaduct | ||
1. | Working Pile | 100% Completed |
2. | Pier Cap Casting | 91% Completed |
3. | Pier Cap Erection | 82% Completed |
4. | U-Girder Casting | 85% Completed |
5. | U-Girder Erection | 53% Completed |
Elevated Station | ||
1. | Working Pile | 100% Completed |
2. | Entry Exit-2 Piling | 89% Completed |
3. | Monolithic Pier | 100% Completed |
4. | Portal Pier (Up to PL) | 100% Completed |
5. | Pier Cap Casting | 67% Completed |
6. | Pier Cap Erection | 33% Completed |
7. | Portal Beam Casting at PL (Cast in Situ) | 67% Completed |
8. | U-Girder Casting | 09% Completed |
ELEVATED RAMP | ||
1. | Elevated Ramp | 15% Completed |
CUT & COVER AND UG RAMP | ||
1 | Cut & Cover | |
a. | Micro Pile | 66% Completed |
b. | Excavation | 20% Completed |
c. | Anchor Drilling & Grouting | 15% Completed |
d. | Waler Erection | 05% Completed |
2 | UG Ramp | |
a. | Capping Beam | 69% Completed |
b. | Excavation | 70% Completed |
UG CSMIA Station | ||
1. | Excavation (m3) | 77% Completed |
2. | Anchor installation & grouting | 76% Completed |
3. | Waler Erection | 68% Completed |
4. | Anchor Stressing | 71% Completed |
Tunnel | ||
1. | Tunnel Ring Segment Casting | 66% Completed |
2. | TBM-1 Main Drive (Down Line) | 21% Completed |
3. | TBM-2 Main Drive (Up Line) | 07% Completed |