Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)

  • Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
 
Length 13.581 km
Stations 10 Nos.
 

Dahisar (E) to Mira-Bhayander ( All Elevated)

1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium

Andheri (E) to CSIA extension

1. Airport Colony (elevated) and 2. CSIA (underground)

Elevated / Underground 11.386 km elevated and 2.195 km underground
Project base cost Rs. 6607 Crore (including state taxes and 7.5% p.a escalation)
Ridership :
2021 Daily Ridership - 8.47 Lakh (PHPDT- 24585)
2031 Daily Ridership – 11.12 Lakh (PHPDT- 30389)
Rolling Stock

Width : 3.20 m

Height : 3.90 m

Length : 21.84 m

Capacity

8 coach train : 2352 persons

Updates as on 28th February 2026

Metro Line 7A

Elevated Viaduct

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Pier 100% Completed
4 Pier Protection 100% Completed
5 Pier Cap Casting 100% Completed
6 Pier Cap Erection 100% Completed
7 U-Girder Casting 100% Completed
8 U-Girder Erection 100% Completed
9 I-Girder Casting 100% Completed
10 I-Girder Erection 100% Completed
11 Deck Slab Casting 100% Completed
12 Parapet Wall Casting 100% Completed
13 Parapet Wall Erection 100% Completed

Elevated Station

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Monolithic Pier (Up to PL) 100% Completed
4 Portal Pier (Up to PL) 100% Completed
5 Pier Cap Casting 100% Completed
6 Pier Cap Erection 100% Completed
7 Portal Beam Casting at PL (Cast in Situ) 100% Completed
8 Tie Beam 100% Completed
9 U-Girder Casting 100% Completed
10 U-Girder Erection 100% Completed
11 Casting of Extended Pier (PL-CL) 100% Completed
12 Casting of Precast Split Pi-Girder 100% Completed
13 Erection of Precast Split Pi-Girder 100% Completed
14 Precast Portal Beam Casting at Concourse Level 100% Completed
15 Casting of T & L Girder 100% Completed
16 Erection of T & L Girder 74% Completed
17 Stitch at Portal Beam 100% Completed
18 Escalator Pit PL to CL 100% Completed

Elevated Ramp

Sr. No. Activity Progress
1 Elevated Ramp 95% Completed

Cut & Cover and UG Ramp

Sr. No. Section Activity Progress
1 UG Ramp Hard Pile 100% Completed
2 Soft Pile 100% Completed
3 Tension Pile 100% Completed
4 Capping Beam 100% Completed
5 Excavation 100% Completed
6 Anchor Drilling & Grouting 100% Completed
7 Waler Erection 100% Completed
8 Anchor Stressing 100% Completed
9 Base Slab 84% Completed
10 Retaining Wall 72% Completed
11 Parapet Wall 23% Completed
12 Cut & Cover Hard Pile 100% Completed
13 Soft Pile 100% Completed
14 Micro Pile 100% Completed
15 Capping Beam 100% Completed
16 Excavation 84% Completed
17 Anchor Drilling & Grouting 83% Completed
18 Waler Erection 71% Completed
19 Anchor Stressing 83% Completed
20 Tension Pile (Casting) 26% Completed
21 Base Slab 6% Completed

Tunnel

Sr. No. Section Activity Progress
1 - Tunnel Ring Segment Casting 100% Completed
2 Main Tunnel
3 Main Tunnel TBM-1 (Down Line) 100% Completed
4 Main Tunnel TBM-2 (Up Line) 100% Completed
5 NATM
6 NATM NATM - 1 0% Completed
7 NATM NATM - 2 0% Completed

UG CSMIA Station

Sr. No. Activity Progress
1 Secant Pile 100% Completed
2 Capping Beam (Rmt) 100% Completed
3 Excavation (m3) 99.2% Completed
4 Anchor Installation & Grouting 96% Completed
5 Waler Erection 88% Completed
6 Anchor Stressing 96% Completed
7 Rock Bolt, Shotcrete, Wire Mesh 93% Completed
8 Tension Pile 100% Completed
9 Base Slab (Sqm) 79% Completed
10 Base Slab to Concourse Slab Wall (Sqm) 81% Completed
11 Column (Base Slab to Concourse Slab) 74% Completed
12 Concourse Slab 51% Completed
13 Concourse Slab to Base Slab Wall 47% Completed
14 Column (Concourse Slab to Roof Slab) 51% Completed
15 Roof Slab 52% Completed
16 Subway-1 Base Slab 100% Completed
17 Subway-1 Wall 100% Completed
18 UPE Wall (Subway-2) 44% Completed
19 Platform Slab 28% Completed
20 OTE Duct Casting 100% Completed

Metro Line 9

Elevated Viaduct

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Pier 100% Completed
4 Pier Cap Casting 100% Completed
5 Pier Cap Erection 100% Completed
6 U-Girder Casting 99% Completed
7 U-Girder Erection 98% Completed
8 Portal Beam Casting 100% Completed
9 Portal Beam Erection 100% Completed
10 I-Girder Casting 100% Completed
11 I-Girder Erection 100% Completed
12 Deck Slab Casting 100% Completed
13 Parapet Casting 100% Completed
14 Parapet Erection 100% Completed

Elevated Station

Sr. No. Activity Progress
1 Working Pile 100% Completed
2 Pile Cap 100% Completed
3 Pier (GL to CL) 100% Completed
4 Pier (CL to PL) 97% Completed
5 Pier (GL to PL) 100% Completed
6 Hammer Head 99% Completed
7 Concourse Pier Arm Casting 100% Completed
8 Concourse Pier Arm Erection 100% Completed
9 Platform Pier Arm Casting 100% Completed
10 Platform Pier Arm Erection 96% Completed
11 Portal Beam Casting (Dahisar Station) 100% Completed
12 Portal Beam Erection (Dahisar Station) 100% Completed
13 U-Girder Casting 99% Completed
14 U-Girder Erection 97% Completed
15 PI-Girder Casting 100% Completed
16 PI-Girder Erection 96% Completed
17 L-Girder Casting 98% Completed
18 L-Girder Erection 97% Completed
19 T-Girder Casting 99% Completed
20 T-Girder Erection 97% Completed

Flyover

Sr. No. Activity Progress
35 Working Pile 100% Completed
36 Pile Cap 94% Completed
37 Pier 98% Completed
38 Hammer Head 100% Completed
39 Abutment Pile 100% Completed
40 Abutment Pile Cap 100% Completed
41 Abutment Pier Cap 100% Completed
42 Dirt Wall 100% Completed
43 Flyover Pier Cap Casting 96% Completed
44 Flyover Pier Cap Erection 100% Completed
45 I-Girder Casting 99% Completed
46 I-Girder Erection 98% Completed
47 Deck Slab Casting 92% Completed