Details of Project

1) Design and Construction of Creek Bridge from Kolshet to Kalher.

Project Information:

  •  Total length of the project:1.640km. and Width : 23.60m
  •  Length of Viaduct : 1175m,
  •  Total Length of Ramp : 465m.
  •  Work completion period : 36 months (including environmental, other statutory clearances and monsoon period)
  •  Defects Liability period : 24 months
  •  Authority Approval: 544 Cr.

Key features of the project.
Kolshet Thane to Kalher Bhiwandi in Thane is the proposed missing link. Kalher
village is connected to the old Agra Road and the area is an industrial area. At
present, the distance of 8.50 km from Kolshet to Kalher (Kolshet-Kapurbawdi-
Balkum-Kashedi-Kalher) takes about 45 minutes.

Current Status:
The preliminary survey work is in progress. The process of obtaining permissions
from land acquisition, forest clearance, Coastal Regulation Zone, Maharashtra
Maritime Board and Railway clearance is in progress.

Project Benefits:

  • Travel time will reduce to about 5 to 7 minutes from presently, 45 min.
  • Saving in travel time and fuels.
  • It will facilitate smooth dispersal of traffic.

2) Construction of 45m DP Road from Taloja MIDC road to Old NH04.

Cost of Project : Rs.98.51 Cr.
Starting Date of Project : 31-01-2024 
Time Limit of Project : 24 months including monsoon 
Completion date : 22/09/2024 
Expected completion date : (EOT till 18/08/2025) 

  • Total Length– 3260 m 
  • Width – 45 m 

Project Feature: 

  • The proposed DP road is located between NH-4 and Taloja MIDC Road, situated on the eastern side of the Mumbai Metropolitan Region (MMR). The project road is in close proximity to Dombivli, Badlapur, and Ambernath regions, with an overall east-west orientation. It lies within the Thane district. 
  • The road starts at Usatane village on Taloja MIDC Road and extends to Wakalan village within Ambernath Taluka limits (as per the revised scope). Currently, the project area has a predominantly rural population. 
  • MMRDA has undertaken the construction of this DP road under its Extended Mumbai 
  • Urban Infrastructure Project (MUIP). The project aims to connect Taloja MIDC Road with the Mumbai-Panvel Highway at Rohinjan Village. 
  • This alignment is virgin and serves as an important route connecting the old MumbaiPune Highway and the Taloja M.I.D.C. Road. 

Present Status: 

  • Physical Progress - 32 % 
  • Financial Progress -28 %

3) Improvement of Chheda Nagar Junction, Ghatkopar East on Eastern Express Highway. 

Brief about the project: 
After completion of SCLR & Eastern frequency, the traffic moving from 
parts of Mumbai to Thane started accumulation at Chheda Nagar Junction at 
Ghatkopar. This created heavy traffic jams there. To resolve this issue, MMRDA 
has undertaken the project of improvement of Chheda Nagar Junction. 


Salient Features: 

  • Project Key Components:
  • Flyover in Sion- Thane direction (3 Lanes) : L-680 m, 12 m 
  • Flyover in Mankhrud. Thane direction( 2 Lane at Level 2): L-1235 m, W 8.5 m 
  • SCLR- Chheda Nagar Flyover Connector ( 2 lane): L-638 m, W- 8.5m 
  • Underpass at Ramabai Nagar (2+2 lanes): L-510m, W- 37.2 m 

Project Cost 

  • The Cost of this project: Rs. 223.85 cr. 
  • Current Progress status:Work is completed and opened for Traffic.
  • Exact Location
  • Chheda Nagar Junction, Ghatkopar East 
  • Completion date: April, 2025 


Importance of the project: 

  • Signal free travel on Eastern Express Highway at Chheda Nagar Junction. 
  • Saving of travel time by 25-30 min. 
  • The project will conserve fuel.

4) Widening and construction of Railway over bridge on Eastern Express Highway at Kopri, Thane 

 

Brief about the project: 
The Eastern Express Highway is crossing the Central Railway near Kopri while passing through Thane city. A 2+2 lane bridge was existing at this place, while 4+4 lane of the Eastern Express Highway are available on both sides of the bridge. Therefore, to remove the large-scale traffic congestion on the railway bridge, the work of widening the railway crossing bridge was undertaken by the Authority. 

As per the project, the widening work of Kopri Railway Bridge has been done in two phases. In the first phase, two-lane bridges have been constructed on both sides of the existing bridge and the traffic has been diverted from these newly constructed bridges and then in the second phase, the existing bridge has been demolished and a new 4-lane bridge has been constructed at that place. In this way, the entire bridge has been constructed for 4+4 lane. 


Salient Features: 

  • Length of Road-796.00 m 
  • Width of Road-37.04 m (4+4 Lane) 
  • Project Cost- Rs. 258.76Cr. 

Current Status: 
Both phases of the project are completed and Opened for traffic. 


Exact Location: 
 Kopri, Thane 


Completion date: 03/07/2023


Importance of the project: 

  • Relief from traffic jam on Eastern Express Highway. 
  • Approximate 30 minutes of time and fuel saving to cross existing railway bridge. 
  • After construction of Vehicular underpass easy movement of traffic from Naupada to Dnyansadhana college towards LBS marg, Wagle estate areas. 
  • Reduction in traffic at Teen Hath Naka. 
  • In future additional lanes can be provided at Anand Nagar Subway.

5) Merging of Thane Ghodbunder Road Main Carriageway with service roads & Concretization of balance width from 
Kapurbawadi to Gaimukh. 


Brief about the project: 
The Ghodbunder Road in Thane district (MH SH-42) starts from Majiwada junction on Eastern Express Highway and connects Western Express Highway at Versova (near Fountain hotel) on National Highway- 8 (Mumbai-Ahmedabad 
highway).The areas surrounding Ghodbunder road are rapidly developing, due to which the vehicular traffic on this road is also increased causing frequent traffic jams along this road. Whereas, both side service roads with asphalt surfaces are comparatively underutilized. Furthermore, from Gaimukh to old Gaimukh Jakat Naka, the width of Ghodbunder road is only about 20 meters having 2+2 lanesrigid pavement. This 1 km stretch is being bottleneck. 


Hence, it is necessary to merge service roads with main carriageway with reconstruction of Rigid Pavement from Kapurbawdi (Ch.0+000 km) to Gaimukh (Ch. 9+350 km. MMRDA has under taken the merging Ghodbunder Road Main Carriageway with service roads & Concretization of balance width from Kapurbawadi to Gaimukh. 


Salient Features: 

  • Length of road - 10.36 Km 
  • Width of road - 6+6 Lanes 
  • The Estimated Cost - 559 Cr.

The project is divided into 4 package as below,

Packages Ch. No. Contract Amount Rs. Contractor Name Length Km
Package-1 0+000 Km to 3+022 Km(Kapurbawadi to Patlipada Flyover 97,28,78,010/- M/s. R.K.Madani& Co 6.044
Package-2 3+022 Km to 5+750 Km (Patlipada Flyover to Hypercity Mall) 98,52,53,990/- M/s Dev Engineers 5.456
Package-3 5+750 Km to 8+290 Km (Hypercity Mall to Nadlabunder Junction) 102,19,73,188/- M/s. Relcon Infraprojects Ltd. 5.08
Package-4 8+290 Km to10+350 Km (Naglabunder Junction to Old Jakat Naka) 97,18,49,858/- M/s. Bitcon India Infrastructure Pvt. Ltd 4.12

Current Status: 
Work in progress- Physical Progress-25%. 


Exact Location: 
Kapurbawadi, Ghodbunder Road Thane 


Completion date: 24 Months


Importance of the project: 

  • Relief from traffic jam on Ghodbunder road. 
  • The project will conserve fuel and time. 
  • This project will reduce travel time.

6) Widening and Strengthening of Roads in Dombivali MIDC Residential area under EXT. MUIP in KDMC area.

Cost of Project Rs. 48.09 Cr
Starting Date of Project 26.12.2022
Time Limit of Project 18 months (Including monsoon)
Completion date 31/12/2023
Proposed Structures Length of road – 4859 m Width -15m & 25m

Project Feature: 

  • The MMRDA has decided to construct proposed DP roads under part of a development planning roads in Cement Concrete material. 
  • Conjunction of traffic will be reduced. 
  • Pollution of Dombivali MIDC Residential Area will be reduced. 
  • Connectivity of internal roads of Dombivali MIDC Residential Area to kalyan shil road and other major road network will be improve. 


Present Status: 
Work completed.

Project Name Construction of 03 Cement Concrete Road works in Kalyan Dombivali Municipal Corporation Area
Brief Description & Salient Features Project Details:
Administrative Approval Cost: Rs. 25.00 Cr.
Contract Cost: Rs. 18.99 Cr.
Length of Roads: 1675 Km
No. of Lanes: 2
Rigid Pavement + Flexible Pavement
SWD on Both sides with Footpath
Cross duct for utilities crossing at every 100 mtr
Contractor: M/s. Yashraj Infrastructure
Work Order Date: 15.10.2024
Project Benefits Reduce traffic and travel time by 10–20 minutes
Saving in fuel
Pothole-free roads
Less maintenance
Current Status Work in progress (35%)
Exact Location Kalyan

7) Construction Of Mankoli – Motagaon Link Road. 

Cost of Project Rs. 83.03 Cr.
Starting Date of Project 13-09-2019
Time Limit of Project 18 months (Including monsoon)
Completion date 31/12/2023
Proposed Structures Length of road – 2890 m

Project Feature: 

  • The MMLR Project start from Mankoli village (at Km 553.300 of NH3) and terminate at Motagaon village. It will connect Kalyan-Dombivli with the shortest route through Bhiwandi and Thane. 
  • The travel time willbe reduced between Dombivali-Bhiwandi-Thane by 15-20 minutes 
  • This will lead a major role in traffic congestion between Dombivali-Thane & other nearby cities. 


Present Status: 
Work Completed. 

8) Design & Construction of Six Lane Bridge across Ulhas creek on Proposed Motagaon- Mankoli Road on Lump Sum Basis in the state of Maharashtra under extended MUIP

Cost of Project Rs.223.25 Cr
Starting Date of Project 14-03-2016
Time Limit of Project 36 months (Including monsoon)
Completion date 31/12/2023
Proposed Structures Total Length– 980m Width- 27m

Project Feature: 
Six-lane bridge being constructed over the Ulhas Creek. It connects Motagaon in Dombivli to Mankoli in Bhiwandi, aiming to significantly reduce travel time and ease traffic congestion between these areas and beyond. Reduction of Travel Time from Thane and Bhiwandi to Kalyan & Dombivali. 


Will divert traffic flow from NH-160 & NH-08 to Khopoli (NH-04) via. Proposed Kalyan Ring Road-Katainaka-Badlapur-Karjat without entering into the habited area of Mumbra, Shilphata, Kalamboli &Panvel. 


Present Status: 
Work completed and opened for public transport.

9) Construction of Proposed 4 nos. of DP Road under Kalyan Growth Center from UsargharNilaje- Ghesar, Nilaje- Kole - Hedutane, Hedutane – Mangoan - Bhopar and Usarghar - Gharivali… MUIP (PKG 1 to 3)

Cost of Project Rs. 326.61 Crs.
Starting Date of Project 26/12/2022
Time Limit of Project 24 months (Including monsoon)
Expected completion date 26/12/2026
Proposed Structures
  • Total Length -13.81Km.
  • Width - 24, 30 and 45 M
Other components These four roads in premises of Kalyan-Shilphata, Badlapur Katai pipeline road, Metro-12 and Virar Alibag Corridor which will improve transportation in these 10 villages

Project Feature: 

  • The State Government sanctioned the Development plan for 27 villages which includes of Kalyan & Ambernath Talukas for total area approx 1089 Hector out of which they now declare Town Planning for 10Villages in Kalyan Growth center. 
  • The proposed work is for construction of new concrete four DP roads under the proposed Kalyan Growth Center having crucial connectivity. 
  • The project roads are also in close proximity to Dombivali and Diva region near to the proposed Mumbai Ahmadabad Bullet Train Thane station which will connect the Dombivali, Ambernath, Taloja and Panvel MIDC.

 
Present Status: 

  • Physical Progress - 28 % 
  • Financial Progress - 30 %

10) Widening and Construction of MIDC road Taloja MIDC road to Ambernath – Katai Naka road Phase II

Cost of Project Rs.212.74 Cr
Starting Date of Project 31/01/2024
Time Limit of Project 24 months (Including monsoon)
Completion date January, 2026
Proposed Structures a) Total Length – 9.550 Km. b) Width of bridge – 15 M

Project Feature: 

  • The project road is located between Taloja MIDC road and Ambernath Katai Naka Road. This part lies on eastern side of Mumbai region. The road is an access road for the industrial stretch along Taloja MIDC industrial corridor. It runs parallel to NH 4 from stretch between shil-phata till Navadephata. 
  • The project road lies in Thane District. The project road starts from Khoni village to Taloja MIDC Road and ends at Nithalas village in Panvel Taluka. Currently the project road has a rural population. MMRDA has decided to construct proposed DP road is part of a development plan road with CC road. 
  • As per the development plan, the project road connects two major highways Taloja-MIDC road and NH4 which results reduction in travel time and congestion at Taloja.

 
Present Status: 

  • Physical Progress - 25% 
  • Financial Progress -20 %

11) Balasaheb Thackeray Rashtriya Smarak

Project Features: 
Phase-1 - Construction of Smarak Structures - 3 buildings and restoration of Existing Mayor’s Bungalow building 
Phase-2 - Technology and IT related work for Museum, Art Galleries, and exterior works.


Phase-1 – Project Cost – Rs. 180.99 Cr 

  • Area of Project: 1,28,011.72 Sqft 
  • One Existing Heritage grade building – Mayor’s Bungalow – Area – 7088.90 sqft 
  • Three new structures constructed namely 
  1. Entrance Block (G+2 Basement) – Area – 33354.49 sqft Ground floor – Meeting rooms 
    1st level basement – Multipurpose hall - Capacity of 205 people 
    2nd Level Basement – Car parking - Stack car park system for 27 cars 
  2. . Interpretation Centre (G+1 Basement) – Area – 16467.53 sqft 
    Ground floor – Open Plaza with water body 
    1st level Basement – Gallery spaces 
  3. Administration Building (G) – Area – 7745.26 sqft 
    It has Balasaheb Thackeray Trust office, conference room, cafeteria and rest rooms for visitors. 
  • Landscape and Hardscaping all round - Area – 101525 sqft It has large area behind Mayor’s Bungalow and around all the buildings with the variety of plants and shrubs. Project also have Amphitheatre back side of the plot along the boundary. 
  • Automation system for gate and security, bag scanner, ticket vending machine, etc. are the other features. 

Present Status: 

  • Phase-1 - Completed on 25th December 2024.

Phase-2 

  • Tender process in in progress.

12) Construction of cement concrete road works in Ulhasnagar Municipal Corporation Area (Package 1, 2 & 3) 

 

  1. Construction of Concrete Road from Netaji Chowk to Kailash Colony via Kurla Camp, Ulhasnagar- 4. (Length 1850 M, Width 22.00 M)
  2. Construction of Concrete Road from New English High School to Lalchakki Chowk via Petrol pump and Hill Line Police station, Ulhasnagar - 5. (Length 1100 M, Width 22.00 M)
  3. Construction of Concrete Road from A- Block to Sai baba Temple via Dolphin Club to Century Ground to Gurudwara, Ulhasnagar – 1. (Length: 950 Width: 22M)
  4. Construction of Concrete Road from Sonar Chowk to Koyande via Sharda Castle, Ulhasnagar - 4. (Length: 330 Width: 18M)
  5. Construction of Concrete Road from Hiraghat Temple to Derbi Hotel vis Samarpan Apartment, Ulhasnagar -3. (Length: 300 Width: 12 M) 
  6. Construction of Concrete Road from Shama Prasad Mukherji Chowk to Shantinagar via Viththalwadi Railway Station, Ulhasnagar - 3. (Length: 1250 Width: 18 M)
  7. Construction of Concrete Road from Wacco compound to Venus chowk, Ulhasnagar - 3. (Length: 2000 Width: 18M & 24 M)


Project Cost: 

  1. PKG-1 - Rs: 48.39 Cr. 
  2. PKG-2 - Rs: 46.28 Cr. 
  3. PKG-3 - Rs: 39.03 Cr. 

Work Order Date: 

  1. PKG-1 – 24-04-2023 
  2. PKG-2 - 24-04-2023 
  3. PKG-3 - 11-04-2023. 

Current Status: 

I. Physical progress: 

  • PKG-1 – 93% 
  • PKG-2 – 91% 
  • PKG-3 – 94% 

II. Financial Progress: 

  • PKG-1 – 72% 
  • PKG-2 – 53% 
  • PKG-3 – 78% 

Project Description 

  1. Project total Length= 7730M 
  2. Main carriage way with M40 PQC.
  3. RCC SWD in M-25 grade concrete with stamped concrete footpath. 
  4. Side Shoulders with 100mm Paver blocks on both sides. 
  5. Traffic management & Traffic Signage’s during construction: Traffic wardens, mandatory cautionary boards, speed limit boards, Road studs etc. 
  6. Street Light Provision. 
  7. Hurdles: 
  • Water Line Shifting Work by UMC. 
  • Sewer line work and property connections. 

 

13) Bharat Nagar BKC, Parallel to Vakola NallahElevated Road from NH-04 (Old) To Katai Naka (Airoli Katai Naka Phase-III) 

Project Feature: 

  • Total length of the project: 6.71 km. 
  • Width: 45 mtr. (3+3 lane with both side service road). 
  • Length of Viaduct: 6158.719 m. 
  • Length of ramps: 1579 m. 
  • Duration of Project Completion: 48 Months 
  • Defect liability period: 24 months 
  • Project Cost: 1981.17 Crores 
  • Date of Commencement: 11-10-2024 
  • Proposed Date of Completion: 10.10.2028 
  • Contractor: M/s. AFCONS Infrastructure Limited 
  • Project Management Consultants: M/s. Smec International Pty. Ltd in Association with Sui Generis Infratech Pvt. Ltd. 


Present Status: 

  • Land Acquisition Process is going on. 
  • DGPS Survey Completed 
  • Topographic Survey is in progress 
  • Geotechnical Investigation is in progress 
  • Casting Yard Development is in progress 
  • CRZ Clearance - Online application uploaded in Parivesh portal on 23-Jun-25, MCZMA committee formed dated 07-Jul-25, Agenda MCZMA published dated 08-Jul-25, MCZMA committee meeting held on 14-Jul-25 and it is agreed to send the proposal to MoEF Delhi. 
  • Forest Clearance - CA land letter submitted to MMRDA dates 20-May-2025, Hon'ble AMC sir has requested dated 10-Jul-2025 to Hon'ble Collector sir of Hingoli for allocation of CA land approximately 3.5 hectare in village Kondhur Taluka Kalamnuri, District Hingoli, Maharashtra. 


Project Major Features: 

  • Up & Down ramp at Diva Shil Road, Katai Naka junction and Badlapur Kalyan Road. 
  • The alignment crosses Mumbai- Ahmedabad bullet train alignment, Central Railway alignment & DFCC alignment.
     

14) Design and Construction of Creek Bridge from Kasarvadavali to Kharbav.


Brief Description: - 

  • The project of “Design and Construction of Creek Bridge from Kasarvadavali to Kharbav was approved in the 156th Authority Meeting held on 05/03/2024 amounting to Rs. 1884.36 crore. 
  • The alignment of the 6-Lane (3 + 3 lanes) elevated project road is of 3.93 Kms which starts from Kasarvadavali in Thane and passes through Thane Creek, Multimodal Corridor (MMC), Dedicated Freight Corridor, crosses Thane Creek, Mumbai Ahmedabad High speed Rail, Diva-asai Existing Railway and meet on State Highway No. 48. Strategic Connectivity: Project crosses Balkum– Gaimukh DP Road at Ch. 2+150; full cloverleaf interchange proposed as per IRC:92 (2017) to ensure seamless movement between two highspeed corridors (80 kmph). 
  • M/s. AFCONS Infrastructure Ltd has been appointed as the contractor on dated 11.10.2024 and M/s. SMEC International Pty. Ltd. in association with M/s. Sui Generis Infratech LLP has been appointed as the Project Management Consultant (PMC) on dated 11.10.2024 for the said project .


Salient Features: 

  • Length of the project: 3.93 km. 
  • Width of super structure = 40 m. (6 lane & 3+3 lane) 
  • Span length = 35 m 
  • The proposed alignment crosses the Thane Creek, Multimodal Corridor (MMC), Dedicated Freight Corridor, crosses Thane Creek, Mumbai Ahmedabad High speed Rail, Diva-Vasai Existing Railway and meet on State Highway No. 48. 
  • Work completion period = 42 months (12 months for Design / Environmental Clearance) + (30 months for Construction) 
  • Defects Liability period (DLP) = 24 months 
  • Project Cost: Rs. 1884.36 Cr 

Present Status: 
 The Geotechnical investigation and preliminary survey work is in progress. The process of obtaining permissions from land acquisition, forest clearance, Coastal Regulation Zone, Maharashtra Maritime Board and Railway clearance is in progress.

 

15) Construction of Grand Memorial of Bharat Ratna Dr. Babasaheb 


Ambedkar at INDU Mill, Dadar, Mumbai The Government of Maharashtra has appointed Mumbai Metropolitan Region Development Authority (MMRDA) as the Special Planning Authority on 19th March 2013 for development of Grand Memorial of Bharat Ratna Dr. Babasaheb Ambedkar on India United Mill no.6, Mumbai, CTS No. 1163 having area about 4.84Ha. Thereafter GoM vide order dated 20th April 2013 issued duties to be performed by MMRDA for this memorial work. 


MMRDA appointed M/s. Shashi Prabhu and Associates and M/s. Design Associates Inc. as Architects/ Consultants for the memorial work with approval of the GoM. The Bhoomipoojan for proposed memorial work was performed at the hands of Hon. Prime minister on 11th October 2015. 


The GoM vide order dated 14th March 2016 constituted Single Member Committee under the Chairmanship of Hon’ble Minister, Social Justice and Special Assistance for finalisation of the plan of proposed Grand Memorial. Accordingly, the Committee had various meetings with all stake holders for finalising the conceptual plan. The Single 
Member Committee has approved the said amended conceptual plan and the same was also approved by GoM by the letter dated 13th April 2017 and accordingly MMRDA was directed for further implementation of the project. MMRDA has taken over the land on behalf of GoM on 25th March 2017 for work. 


MMRDA has given administrative approval to approx. Cost of ₹600 Cr. for construction of the Memorial. The tenders were invited on 14th April 2017 on design build basis for Construction of Grand Memorial for Dr. Babasaheb Ambedkar on INDU Mill land. However, only one bid was received hence as per rule, tender was re-invited. Based on the recommendations of IIT Mumbai, changes were made to the iron and structural steel to be used for the memorial, resulting in a revised estimated cost of ₹622.40 crore. 


The bid of M/s. Shapoorji Pallonji and Co Ltd was received in retender. The Executive Committee of MMRDA has approved bid amounting ₹709 Cr of M/s. Shapoorji Pallonji and Co Ltd. MMRDA in its Authority meeting accorded revised administrative approval to cost of ₹763.05 Cr. The work order to contractor was issued on 9th February 2018

Based on the final approved concept plan, the memorial comprises of following components:

  • Entrance Plaza Building with Information centre, Ticketing Counter, Cloak room, Rest rooms, Security counter, Souvenir Shop, Restaurant and Control room. 
  • Monument Building having Pedestal 100ft high plus Bronze Statue height increased from 250ft to 350ft, The total height of monument is 450ft. 
  • Auditorium (capacity-1000 seats) 
  • Research Centre with Seminar Halls and Library 
  • Meditation Area & Promenade 
  • Parikrama Path 
  • 2 level Basement for vehicle parking (capacity-460 vehicles)

The revised conceptual plan of the grand memorial of Bharat Ratna Dr. Babasaheb Ambedkar at Indu Mill was presented in the GoM cabinet meeting on 15th January 2020 and was approved. As per the revised plan, the height of the statue in the grand memorial has been increased, with the pedestal being 30 meters (100 feet) high and the statue 106.68 meters (350 feet) tall, making the total height 136.68 meters (450 feet). As per the revised concept, the estimated project cost has been revised from ₹763.05 crore to ₹1089.95 crore.

State GoM established sub-committee complete monitor of project vide Govt. resolution Meeting formed no. 2020/   .   .40/           . 09   , 2022. The Chairman of this sub-committee members is Hon’ble Minister (Social Justice), Hon’ble Minister (Urban Development), Hon’ble Minster (School Education) and other Hon’ble ministers.

Project review meeting of the cabinet sub-committee on completed on 11th May 2022 at the site. The Cabinet Sub-Committee reviewed the work of the project and decided to visit the 25-feet statue model completed at Ghaziabad.

The cabinet sub–committee visited Shri. Ram Sutar studio on 19th May 2022 at Ghaziabad to review the 25ft statue model. During the visit the members of the Cabinet sub-committee provided few suggestions/comments. After incorporating the suggestions/comments provided by the Cabinet sub-committee, photographs of the statue were presented in the third review meeting held on 15th June 2022.

Hon. Members of statue committee and officials from Social Justice and Special Assistance Department, GoM visited the Shri. Ram Sutar studio on 7th September 2022 and few minor corrections where suggested. Accordingly, statue sculptor has incorporated the minor corrections and statue model is kept ready for final approval.

Hon. Chief Minister and Hon. Deputy Chief Minister site visit and review meeting of Ambedkar memorial at Indu Mill conducted on 16th November 2022. During the discussion, the Hon. Metropolitan Commissioner raised the issue of Pending approval of 25 feet Statue model. It was decided that a new committee will be constituted by the government for the said subject. The committee will include some members of the Ambedkar family and persons from the Ambedkar movement. It was decided that the said dignitaries will visit the 25 feet Statue model and submit its report/approval to the government and thereafter the government will approve the same.

Hon. Chief Minister and Hon. Deputy Chief Minister, according to the instructions given by the finalize the statue with the approval of the Hon. members of Dr. Babasaheb Ambedkar's family, public representatives, as well as dignitaries from the Ambedkar movement and others on 6th April, 2023. The meeting was held at Mr. Ram Sutar studio Ghaziabad, New Delhi.

During the present visit, all dignitaries had the opportunity to witness the 25 feet statue representation (350 feet statue of Dr. Babasaheb Ambedkar at the Indu Mill Memorial) created by Shri. Ram Sutar studio in Ghaziabad, Uttar Pradesh. After observing the statue, the dignitaries present gave their final approval. Subsequently, on 17th May 2023 the formal approval was issued through official correspondence, and as per that, the concerned authorities have informed the project contractors to expedite the work on the statue to ensure its timely completion.

As per the decision of the Department of Social Justice and Special Assistance, Government of Maharashtra,                .      2021/    .   .15/         , dated. 10th August 2023 the final approval has been granted to create a 350 feet statue on the ground of the 25 feet statue representation created by Shri. Ram Sutar studio.

As per the directions given in the Cabinet Sub-Committee meeting held on 15th May 2022, a proposal amounting to an estimated cost of ₹23.77 crore for the works related to internal use of the library and lecture halls (4) in the Research Centre has been submitted to the Social Justice and Special Assistance Department for administrative approval on 6th October 2022.

As per the revised master plan all statutory permissions have been taken & completed. The work of memorial is in progress. Till date Ancillary buildings 85% work is completed (Structural works completed & finishing works in progress) and monument pedestal & statue work 28.5% completed & balance work is in progress. Also, the external development and landscaping works within the project premises are in progress.

Till date, an expenditure of ₹531.47 crore has been incurred on the project. Budget provision for the project made by MMRDA for 2025-26 is ₹500 Cr.

Till date an amount of ₹548.71 Cr has been received from Social Justice and Special Assistance department, GOM towards reimbursement of project expenditure.

16) Design and Construction of Elevated Road from Kalyan-Murbad Road (Palms Water Resort) to Badlapur Road (Jagdish Dughdhalaya) to Pune Link Road parallel to Waldhuni River Crossing Over Karjat-Kasara Railway Line Including Slip Road.

Project Information:- 

  • Elevated road including ramp and arms length – 4.30 km
  • Slip road length (ROW-24m) – 1.90 km
  • Road Work (ROW-18m)- 0.80 km R.C.C Retaining Wall – 2.48 km
  • No of ROBs : 02 No. of Junctions: 03 (Bhavani Chowk, Jagdish Dughdhalaya & Vitthalwadi)
  • Lane Configuration : Four (2+2) Lane Road 

Benefits of the Project:

  •  Reduce traffic & travel time by 25 mins. 
  •  Better East- West connectivity for Kalyan city. 
  •  It will facilitate smooth dispersal of traffic.
  •  Saving in fuel. 

 
 Project Cost: 

  • Administrative Approval Cost: Rs 642.98 Cr 
  • Contract cost Rs 474.10 Cr 
  • Contractor: M/s Ashoka buildcon Ltd 
  • PMC: M/s Lion Engineering Consultants Pvt. Ltd. 

Commencement Date: 11 October 2024. 
Stipulated Completion Date: 10th April 2027
Physical Progress : 11.45 % 
Financial Progress : 10.13% 

Present status of project:

  •  Confirmatory bore holes of 101 nos completed out of 140nos, Pile- 129 nos completed out of 605 nos, Pile cap –20 nos completed out of 140nos, Pier – 20 nos completed out of 194 Nos, Girder casting – 13nos completed out of 483nos.
  •  GAD in principle approval From Railways - ROB at Kalyan-Karjat & ROB Kalyan-Kasara 
  • Railway Line is in progress through KDMC.
  •  Land Acquisition is being progress by KDMC.
  •  Utilities shifting from concerned utility department.

17) Design & Construction of Sewri to Worli Elevated Connector Project.

Project Feature :- 

  • Mumbai Metropolitan Region Authority (MMRDA) is implementing the Sewri Worli 
  • Elevated Connector as a part of traffic dispersal system of Mumbai Trans Harbour Link 
  • project 
  • The proposed Link is 4 Lane Elevated Corridor having a length of 4.5 Km 
  • This link will provide the direct connectivity of Mumbai Trans Harbour Link project with Bandra Worli Sea Link and Coastal road project on west coast of Mumbai. 

Salient Features:- 

  • Work order date – 13 January 2021 
  • Total Length of Connector- 5.964 km. 
  • Width of Connector – 17 m 
  • Speed Limit – 80 km/hr. 
  • Type of Superstructure – Segmental Type 
  • Obligatory- Steel Composite 
  • ROB at Sewri- 81.117 m. 
  • ROB at Elphinstone- 132.200 m. 
  • Expected Completion date- 12 January 2026 

Project Cost: 

  • Revised Administrative Approval Cost 2283.53 Cr. 
  • Contract Cost 1051.86 Cr. 
  • ROB Cost 214 Cr. 
  • Contractor M/s. J Kumar Infraproject Ltd. 
  • PMC M/s Assystem stup 

Progress 

  • Physical Progress- 61 % 
  • Financial Progress- 59 % 

Project Benefits 

  • SWEC will connect MTHL and Bandra Worli Sea link/ Coastal Road 
  • This will become only one Signal free elevated corridor 
  • The commuters from Navi Mumbai to Central & South Mumbai will have benefits in terms of 
  • time-saving & mostly trouble-free ride. 
  • Travel from city to Navi Mumbai will be easier. 
  • Long distance travelers from western suburban going towards Goa & South India are likely to use Bandra Worli Sea Link, Sewri-Worli Connector – MTHL. 
  • The SWEC Project will contribute about 15 to 20% of the vehicular traffic on MTHL 
  • Due to SWEC, approximately 35 to 45 thousand motorists will benefit daily. 
  • Connector will facilitate, Speedy & safe travel, there will be substantial savings in time & fuel. 

 

18) Name of the Project: Construction of Elevated Eastern Freeway Extension from Chheda Nagar, Ghatkopar to Anand Nagar, Thane

   Brief Description: -

  •     The project of “Construction of Elevated Eastern Freeway Extension from Chheda Nagar, Ghatkopar to Anand Nagar, Thane was approved in the 156th Authority Meeting held on 05/03/2024 amounting to Rs. 3314.40 crore. 
  •     The alignment of the 6-Lane (3 + 3 lanes) elevated project road is of 13.900 Kms which starts from Ananad Nagar near Thane and passes through Mulund, Airoli, JVLR, Kanjurmarg, Vikhroli, Ghatkopar and ends at Chheda Nagar. The Provision of elevated 3+3 Lanes toll plaza near Navghar Flyover, For South bound traffic 2 Lane Up-down ramps are proposed near Mulund Check Naka, near Airoli Junction, near Vikhroli Junction. 
  •     The Eastern Freeway Extension elevated corridor has to merged with Anand Nagar to Saket Elevated Road at Mulund Octroi naka.
  •     M/s. Navayuga Engineering Company Limited has been appointed as the contractor on dated 18.12.2024 and M/s. Sheladia Associates Inc. in association with M/s. SMEC International Pty. Ltd, has been appointed as the Project Management Consultant (PMC) on dated 18.12.2024 for the said project 

    Salient Features:

  •     Length of the project: 13.90 km.
  •     Width of super structure = 25 m. (6 lane & 3+3 lane) 
  •     Span length = 40 m
  •     The proposed alignment crosses the Mulund, Airoli, JVLR, Vikhroli, Godrej Junction, Mankhurd, Ghatkopar & Chheda Nagar.
  •     Work completion period = 48 months (12 months for Design / Environmental Clearance) + (36 months for Construction)
  •     Defects Liability period (DLP) = 24 months
  •     Project Cost: Rs. 2682 Cr

Present Status:
        Preliminary survey works and Test Pile is completed and Geotechnical Investigation Work, Utility Identification work and Working pile is in progress. 

19) Name of the Project:- Construction of Balkum to Gaimukh NH3 Connector Ghodbunder     By Pass DP road (Thane Coastal Road)


   Brief Description: -

  •     The project “Construction of Balkum to Gaimukh NH3 Connector Ghodbunder By-pass DP road (Thane Coastal Road)” was approved in the 156th Authority Meeting held on 05/03/2024 amounting of Rs. 3364.62 crore
  •     The proposed 6-lane road (Greenfield alignment) of total length of 13.450 km. The Project starts near Balkum at Kharegaon toll plaza on Mumbai Nashik highway (old NH-3) Ch.0/000 and ends at Gaimukh Ch. 13/450.
  •     The road experiences heavy commercial traffic often leading to traffic congestion and frequent jams. Moreover, the ongoing urbanization along Ghodbundar Road has substantially increased passenger traffic, further exacerbating the situation. The heavy commercial vehicles like trucks and trailers has led to a decline in the road's level of service, resulting in recurring traffic bottlenecks and congestion. 
  •     It is therefore proposed to provide a new road (Greenfield alignment) along the coastline of the Thane creek so that the commercial traffic on Ghodbundar Road can be separated.
  •     M/s. Navayuga Engineering Company Limited has been appointed as the contractor on dated 18.12.2024 and M/s TEC4 Ingenieros India Private Limited in association with M/s Yooshin Engineering Corporation, has been appointed as the Project Management Consultant (PMC) on dated 18.12.2024 for the said project 

   Salient Features:

  •     Length of Alignment : 13.450 km 
  •     Work completion period = 48 months (12 months for Design / Environmental Clearance) + (36 months for Construction)
  •     Defects Liability period (DLP) = 24 months
  •     Project Cost: Rs. 2727 Cr

   Present Status:
        Preliminary survey works and Test Pile is completed and Geotechnical Investigation Work, Utility Identification work and Working pile is in progress. 
  
  


  20)Project Name:¬Construction of Elevated Road in Thane City from Anand Nagar to Saket on Eastern Express Highway


Brief about the project: 
Eastern Express Highway in Thane passes through important junctions as Teenhath Naka, Nitin Junction, Cadbury junction, golden dyes junction (Majiwada). There are 6 lanes flyover at Teen hath Naka junction, Cadbury flyover at Nitin and Cadbury junction, Golden dyes Flyover over Majiiwada junction. At Teen hath Naka there are two roads coming from Thane and road coming from LBS marg. Also, there service roads with to and Fro traffic and slip roads of flyovers. At Majiwada junction, prominent Ghodbunder road. which carries traffic from Mumbai to Gujarat and Nashik to Gujarat. Major connectivity to Mumbai Ahmedabad Highway. Due to heavy to and fro traffic from Mumbai and addition of major traffic due to this junction there are frequent traffic congestion on Eastern Express Highway in Thane.
Salient Features:
1.    Length: 8.24 km (3+3 traffic lanes)
2.    Time Period: 48 Months
3.    Accepted cost is Rs. 1847.72 Cr.
Current Status:
Geotechnical Investigation, Utility identification & TestPilesworks are completed. Piles work is in progress. 
Exact Location:
Anand Nagar toSaket, Thane
Importance of the project:

  •     To decongest the traffic at Thane. 
  •     The project will conserve fuel.
  •     This project will reduce travel time.


21)Name of the Project: Design & Construction of Creek Bridge from Gaimukh to Payegaon in Thane and Bhiwandi

Brief Description: -

  •   The project of “Design & Construction of Creek Bridge from Gaimukh to Payegaon in Thane and Bhiwandi was approved in the 156th Authority Meeting held on 05/03/2024 amounting to Rs. 1551.18 crore. 
  •     The alignment of the 4-Lane (2 + 2 lanes) elevated project road is of 6.506 Kms which starts from Thane creek near gaimukh in Thane and further passes through Mumbai Ahmebabad High Speed Rail, Multimodal Corridor (MMC), Diva – Vasai Existing Railway, Dedicated Freight Corridor and Anjur Chinchoti Road and terminates near Payegaon Village.
  •     M/s. Ashoka Buildcon Limited has been appointed as the contractor on dated 14.10.2024 and M/s. Sheladia Associates Inc. has been appointed as the Project Management Consultant (PMC) on dated 14.10.2024 for the said project 

 Salient Features:

  •     Length of the project: 6.509 km.
  •     Work completion period = 42 months (12 months for Design / Environmental Clearance) + (30 months for Construction)
  •     Defects Liability period (DLP) = 24 months
  •     Project Cost: Rs. 975.580 Cr (Excluding GST)

Present Status:
        Topographic Survey is completed. Geotechnical investigation, fabrication of barges, construction of temporary access bridge are in progress.

 

22)

Project Name Construction of 03 Cement Concrete Road works in Kalyan Dombivali Municipal Corporation Area
Brief Description & Salient Features Project Details:
Administrative Approval Cost: Rs. 25.00 Cr.
Contract Cost: Rs. 18.99 Cr.
Length of Roads: 1675 Km
No. of Lanes: 2
Rigid Pavement + Flexible Pavement
SWD on Both sides with Footpath
Cross duct for utilities crossing at every 100 mtr
Contractor: M/s. Yashraj Infrastructure
Work Order Date: 15.10.2024
Project Benefits Reduce traffic and travel time by 10–20 minutes
Saving in fuel
Pothole-free roads
Less maintenance
Current Status Work in progress (35%)
Exact Location Kalyan

 23)

Project Name Construction of Cement Concrete Road works in Kalyan Dombivali Municipal Corporation Area (Package 3C)
Brief Description & Salient Features Project Details:
Administrative Approval Cost: Rs. 332.05 Cr.
Contract Cost: Rs. 63.54 Cr.
Length of Roads: 4.672 Km
No. of Lanes: 2
Rigid Pavement + Flexible Pavement
SWD on both sides with Footpath
Cross duct for utilities crossing at every 150 mtr
Contractor: M/s. Bitcon India Infrastructure Developers Pvt. Ltd.
PMC: M/s. Mahimtura Consultant Pvt. Ltd.
Commencement of Work: 26.12.2022
Project Benefits Reduce traffic and travel time by 10–20 minutes
Saving in fuel
Pothole-free roads
Less maintenance
Current Status Work in progress (94%)
Exact Location Kalyan East and Dombiwali West

 

24)Project Name: Design & Construction of Up ramp connecting to Airoli Katai Naka flyover near Bharat Bijlee Junction on Thane Belapur Road.

Project Features:

  •     Length of Up Ramp- 521.60 Rmt.
  •     Length of Down Ramp- 340.00 Rmt.
  •     Width of Carriageway- 7.50 Rmt.
  •     No. of Lanes- 2 Nos.
  •     Project Cost: 49.90 Cr. & Rev. Cost: 59.79 Cr.

Interchange Stations:

  •     Not Applicable

Present Status:

  •     Overall, 30.00 % Civil works completed.
  •     Financial Progress: 27.40 %

Expected Completion date:

  •     Phase I Up & Down Arm- 31st March 2026

Project Major Features:

  •     Enable seamless traffic movement from Thane Belapur Road towards Mulund via the Up Ramp.
  •     Provide direct and uninterrupted connectivity between Airoli and the Airoli–Katai Naka Flyover for vehicles traveling to and from the Mulund direction.

Project Major Challenges:

  •     This Up & Down arm project is being executed in heavy traffic on Thane Belapur Road, Navi Mumbai.
  •     Both Up & Down arm steel curve girders launching will be done on the busiest Thane Belapur Road.

 

25)Construction of Grand Memorial of Bharat Ratna Dr. Babasaheb Ambedkar at INDU Mill, Dadar, Mumbai

The Government of Maharashtra has appointed Mumbai Metropolitan Region Development Authority (MMRDA) as the Special Planning Authority on 19th March 2013 for development of Grand Memorial of Bharat Ratna Dr. Babasaheb Ambedkar on India United Mill no.6, Mumbai, CTS No. 1163 having area about 4.84Ha. Thereafter GoM vide order dated 20th April 2013 issued duties to be performed by MMRDA for this memorial work.

MMRDA appointed M/s. Shashi Prabhu and Associates and M/s. Design Associates Inc. as Architects/ Consultants for the memorial work with approval of the GoM. The Bhoomipoojan for proposed memorial work was performed at the hands of Hon. Prime minister on 11th October 2015.

The GoM vide order dated 14th March 2016 constituted Single Member Committee under the Chairmanship of Hon’ble Minister, Social Justice and Special Assistance for finalisation of the plan of proposed Grand Memorial. Accordingly, the Committee had various meetings with all stake holders for finalising the conceptual plan. The Single Member Committee has approved the said amended conceptual plan and the same was also approved by GoM by the letter dated 13th April 2017 and accordingly MMRDA was directed for further implementation of the project. MMRDA has taken over the land on behalf of GoM on 25th March 2017 for work.

MMRDA has given administrative approval to approx. Cost of ₹600 Cr. for construction of the Memorial. The tenders were invited on 14th April 2017 on design build basis for Construction of Grand Memorial for Dr. Babasaheb Ambedkar on INDU Mill land. However, only one bid was received hence as per rule, tender was re-invited. Based on the recommendations of IIT Mumbai, changes were made to the iron and structural steel to be used for the memorial, resulting in a revised estimated cost of ₹622.40 crore.

The bid of M/s. Shapoorji Pallonji and Co Ltd was received in retender. The Executive Committee of MMRDA has approved bid amounting ₹709 Cr of M/s. Shapoorji Pallonji and Co Ltd. MMRDA in its Authority meeting accorded revised administrative approval to cost of ₹763.05 Cr. The work order to contractor was issued on 9th February 2018.

Based on the final approved concept plan, the memorial comprises of following components.

  • Monument Building having Pedestal 100ft high plus Bronze Statue height increased from 250ft to 350ft, The total height of monument is 450ft.
  • Auditorium (capacity-1000 seats)
  • Research Centre with Seminar Halls and Library
  • Meditation Area & Promenade
  • Parikrama Path
  • 2 level Basement for vehicle parking (capacity-460 vehicles)

The revised conceptual plan of the grand memorial of Bharat Ratna Dr. Babasaheb Ambedkar at Indu Mill was presented in the GoM cabinet meeting on 15th January 2020 and was approved. As per the revised plan, the height of the statue in the grand memorial has been increased, with the pedestal being 30 meters (100 feet) high and the statue 106.68 meters (350 feet) tall, making the total height 136.68 meters (450 feet). As per the revised concept, the estimated project cost has been revised from ₹763.05 crore to ₹1089.95 crore.

State GoM established sub-committee complete monitor of project vide Govt. resolution Meeting formed no. 2020/प्र.क्र.40/बांधकामे दि. 09 मे, 2022. The Chairman of this sub-committee members is Hon’ble Minister (Social Justice), Hon’ble Minister (Urban Development), Hon’ble Minster (School Education) and other Hon’ble ministers.

Project review meeting of the cabinet sub-committee on completed on 11th May 2022 at the site. The Cabinet Sub-Committee reviewed the work of the project and decided to visit the 25-feet statue model completed at Ghaziabad.

The cabinet sub–committee visited Shri. Ram Sutar studio on 19th May 2022 at Ghaziabad to review the 25ft statue model. During the visit the members of the Cabinet sub-committee provided few suggestions/comments. After incorporating the suggestions/comments provided by the Cabinet sub-committee, photographs of the statue were presented in the third review meeting held on 15th June 2022.

Hon. Members of statue committee and officials from Social Justice and Special Assistance Department, GoM visited the Shri. Ram Sutar studio on 7th September 2022 and few minor corrections where suggested. Accordingly, statue sculptor has incorporated the minor corrections and statue model is kept ready for final approval.

Hon. Chief Minister and Hon. Deputy Chief Minister site visit and review meeting of Ambedkar memorial at Indu Mill conducted on 16th November 2022. During the discussion, the Hon. Metropolitan Commissioner raised the issue of Pending approval of 25 feet Statue model. It was decided that a new committee will be constituted by the government for the said subject. The committee will include some members of the Ambedkar family and persons from the Ambedkar movement. It was decided that the said dignitaries will visit the 25 feet Statue model and submit its report/approval to the government and thereafter the government will approve the same.

Hon. Chief Minister and Hon. Deputy Chief Minister, according to the instructions given by the finalize the statue with the approval of the Hon. members of Dr. Babasaheb Ambedkar's family, public representatives, as well as dignitaries from the Ambedkar movement and others on 6th April, 2023. The meeting was held at Mr. Ram Sutar studio Ghaziabad, New Delhi.

During the present visit, all dignitaries had the opportunity to witness the 25 feet statue representation (350 feet statue of Dr. Babasaheb Ambedkar at the Indu Mill Memorial) created by Shri. Ram Sutar studio in Ghaziabad, Uttar Pradesh. After observing the statue, the dignitaries present gave their final approval. Subsequently, on 17th May 2023 the formal approval was issued through official correspondence, and as per that, the concerned authorities have informed the project contractors to expedite the work on the statue to ensure its timely completion.

As per the decision of the Department of Social Justice and Special Assistance, Government of Maharashtra, शासन निर्णय क्र. बैठक 2021/ प्र.क्र.15/ बांधकामे, dated. 10th August 2023 the final approval has been granted to create a 350 feet statue on the ground of the 25 feet statue representation created by Shri. Ram Sutar studio.

As per the directions given in the Cabinet Sub-Committee meeting held on 15th May 2022, a proposal amounting to an estimated cost of ₹23.77 crore for the works related to internal use of the library and lecture halls (4) in the Research Centre has been submitted to the Social Justice and Special Assistance Department for administrative approval on 6th October 2022

As per the revised master plan all statutory permissions have been taken & completed. The work of memorial is in progress. Till date Ancillary buildings 85% work is completed (Structural works completed & finishing works in progress) and monument pedestal & statue work 28.5% completed & balance work is in progress. Also, the external development and landscaping works within the project premises are in progress.

Till date, an expenditure of ₹531.47 crore has been incurred on the project. Budget provision for the project made by MMRDA for 2025-26 is ₹500 Cr.

Till date an amount of ₹548.71 Cr has been received from Social Justice and Special Assistance department, GOM towards reimbursement of project expenditure.

 

26)Construction of Elevated Corridor from a) Kurla to Vakola flyover on SantacruzChembur Link Road covering Vakola junction, University junction and BKC junction & b) MTNL junction, BKC to LBS flyover at Kurla.

Project Information:

SSantacruzChembur Link Road (SCLR) has been planned Under the Mumbai Urban Infrastructure Project (MUIP)to have east west connectivity to support the essential flow of the trafficwithin a dominating commercial hub at BKC. SCLR is connecting BKC to Eastern Express Highway and Western Express Highway through an elevated corridor. This road covers four junctions, i.e. BKC Junction, University Junction, Dr.AmbedkarChowk, &Vakola Junction.

Cable Stayed bridge at Vakola junction over WEH

Mumbai Metropolitan Region Development Authority (MMRDA) hasConstructed a Cable stayed bridge to have a signal free East-West corridor connectivity and to cater the traffic flow coming from Navi Mumbai, EEH and from BKC towards Airport, with continuous superstructure of 215m length which is a part of SCLR Extension Phase-I Project and also it is south Asia’s first sharp curvature span of 100m radius which includes orthotropic steel deck supported by stay cables, which will cross over WEH at the height of 25m from ground level. Where its diagonal cables transfer the vertical load from the deck directly to the Pylon and reducing the supports of pier beneath. The width of bridge varies from 10.5m to 17.2m, having carriage way of 2 lanes. The main element of a cable stayed bridge is Pylon (Y Shape), Steel deck, stay cable, anchorages.

R.No Feature Details
1 Project Management Consultant M/s. PADECO Co. Ltd.
2 Contractor M/s. J Kumar Infraprojects Ltd.
3 Length of Elevated Road
  • A) MTNL Arm: 2-lane from BKC to LBS Flyover (2nd level) – 1.2 km (Open to traffic on 10.02.2023)
  • B) 4-lane from Forensic Laboratory to Kapadia Nagar – 1.65 km, and Kapadia Nagar to Vakola down ramp (2-lane) – 1.0 km (Open to traffic on 13.04.2023)
4 Length to be Opened for Traffic 2-lane from Mumbai University (North Gate) to Pan Bai International School – 1.66 km (2nd level)
5 Travel Time Reduced 45 minutes & saving fuel
6 Type of Foundation Pile foundation / Open foundation
7 Type of Substructure RCC Pier (Single central / Cantilever / Portal), Pylon for cable-stay
8 Type of Superstructure
  • RCC segmental box girder / Steel composite / Orthotropic steel deck (cable-stayed bridge)
  • Galvanized 7-wire PC strand 15.7 mm dia with HDPE sheathing and wax coating for stay cable
9 Project Cost Rs. 670 Cr
10 Project Start Date 27 October 2016
11 Date of Completion July 2025
12 Overall Physical Progress 100%
13 Financial Progress 96%

 

27)Design and Construction of elevated corridor from Bharat Diamond Bourse Company, University to Vakola Junction. (SCLR Phase-II)

Brief Description:

The growth of commercial complexes at BKC is Phenomenal. The major corporate has established their head offices in this part of the city from all sectors including ICICI Bank, Dena bank, Wokhard, International convention centre of Reliance, Bharat diamond bourse, National Stock Exchange, State Bank of India, Nabard, U.S. consulate etc. being in the geographical centre of the city, there are traffic flows from all direction converging to BKC. The arterial road around the BKC has reached the traffic saturation in shortest time and it is essential to connect BKC to Eastern Express Highway, Western Express highway through an elevated corridor.

Under the Mumbai Urban Infrastructure Project (MUIP), this need has been already envisaged and an Elevated Road on Santacruz-Chembur Link Road covering four junctions, i.e. BKC Junction, University junction, Dr. Ambedkar Chowk; Vakola Junction and also MTNL Junction, joining BKC to Lal Bahadur Shastri Marg is proposed. This highend traffic study has confirmed the need of the elevated corridor to have east west connectivity to support the essential flow of the traffic within this dominating commercial hub at BKC.

Salient Features of Project:

Particular Details
Client Mumbai Metropolitan Region Development Authority (MMRDA)
Project Management Consultant PADECO Co. Ltd., Japan (From Jan 2020 to Till Date)
Contractor M/s. Niraj Cement Structurals Ltd.
Connectivity From BKC to Western Express Highway
Length of Elevated Road
  • 4 Lane from Bharat Nagar to University Gate No. 2, 0.50 Km (Width 17.2 m)
  • 2 Lane from University Gate No. 2 to Merging with SCLR Phase-I & Western Express Highway, 0.90 Km (Width 8.5 m)
  • Total = 1.40 Km
Travel Time Reduced 35 minutes
Type of Foundation Pile Foundation / Retaining wall in Ramp portion
Type of Substructure RCC Pier (Single central / Cantilever / Portal)
Type of Superstructure RCC PSCI Girder / Steel composite span
Cost put to Tender Rs. 245.91 Crore
Tender Cost Original Cost 220.89 Cr (10.17% below)
Revised Cost Rs. 191.88 Cr
Project Start Date 18th October, 2017
Stipulated Period of Work 30 months
Date of Completion 31st December, 2025 (EOT granted)
Current Status On going
  • Physical Progress – 75%
  • Financial Progress – 73%
Location Bharat Nagar BKC, Parallel to Vakola Nallah

28)Kalyan Ring Road (Seg-III From Motagaon Bridge to Govind wadi Bypass)

Kalyan Ring Road (KRR) is a Kalyan Dombivali Municipal Corporation (KDMC) approved DP alignment, starts at Hedutane Village on Badlapur-Katai Road, Crosses Shil-Kalyan-Bhivandi Road near Bhopar village, Diva-Vasai Railway loop line & CRly line Kopar Railway station vicinity, connects Motagaon-Mankoli link road, crosses Diva-Vasai Railway line, follows further alignment parallel to Ulhas River, connects Shil-Kalyan-Bhivandi Road near Durgadi Bridge & ends at Titwala. To & fro Traffic coming from Padgha-Nashik highway & Gujarat state and Pune & Karnataka state, currently plying through KDMC’s internal Road will get diverted through this KRR new link thereby expecting decongesting KDMC’s internal traffic. Road Construction work is undertaken from Durgadi Chowk to Titwala (16.40 km) & Road Construction work from Motagaon Bridge to Govind wadi Bypass is being tendered. Road construction work from Badlapur Katai Road to Motagaon Bridge is to be undertaken. Making incumbent free RoW land is the responsibility of KDMC

Project Beneficiaries:

  • Connectivity from Katai Badlapur Road, Kalyan Shil Road, Panvel Shil Road to NH-3, decongestion of other internal roads in KDMC area & reduction in vehicular pollution is expected.
  • Reduction of travel time 30 min expected.

Project Component:

  • Length: At Grade Road: 3.58 km Stilt Road: 2.28 Km Total: 5.86 Km
  • RoW width: 45 M
  • Bituminous Carriage way 02 + 02 lanes & unpaved carriageway in balance lanes
  • Storm Water Drain along both side RoW
  • Footpath along both side Row.

Project Cost & Completion Details:

  • Administrative Approval estimate value: Rs. 661.36 Cr.
  • Cost of Work: Rs.598.12Cr.
  • Date of Work Order: 12/12/2023
  • Time period: 36 Months Including monsoon
  • Expected Date of Completion: 12/12/2026
  • Contractor Name: M/s Rithwik – RPS JV
  • Consultant Name: M/s Technogem Consultant Pvt. Ltd.

Current progress of work:

  • Physical Progress of project – 15%
  • Financial Progress of project – 13%

29)

Project Name Construction of Cement Concrete Roadworks in Kalyan Dombivali Municipal Corporation Area. (Package 1A).
Brief description and silent feature
  • Project Details
  • Administrative Approval Cost Rs. 332.05Contract Cost Rs. 77.74 Cr.
  • Administrative Approval Cost Rs. 332.05 Contract Cost Rs. 77.74 Cr.
  • No. of Lane- 2
  • Rigid Pavement + Flexible Pavement
  • SWD on Both sides with Footpath.
  • Cross duct for utilities crossing at every 150 mtr.
  • Contractor – M/s. Ashwini Infra-development Pvt. Ltd.
  • PMC- M/s. Mahimtura Consultant Pvt Ltd.
  • Commencement of work- 21.12.2022
  • Project Benefits-
  • Reduce Traffic and travel time by 10 to 20 min
  • Saving in Fuel.
  • Pot hole free roads
  • Less Maintenance.
Current Status Work in progress (84 %)
Exact Location Dombivli East

30)

 

Project Name Construction of Cement Concrete Road works inKalyan Dombivali Municipal Corporation Area. (Package 2).
Brief description and silent feature
  • Project Details
  • Administrative Approval Cost Rs. 332.05Contract Cost Rs. 62.63 Cr.
  • - Length of Roads- 4.008 Km.
  • No. of Lane- 2
  • Rigid Pavement + Flexible Pavement
  • SWD on Both sides with Footpath.
  • Cross duct for utilities crossing at every 200 mtr.
  • Contractor – M/s. RPS Infraproject Pvt. Ltd.
  • PMC- M/s. Pentacle Consultant (I) Pvt Ltd.
  • Commencement of work- 26.12.2022
  • Project Benefits-
  • Reduce Traffic and travel time by 10 to 20 min
  • Saving in Fuel.
  • Pot hole free roads
  • Less Maintenance.
Current Status Work in progress (97 %)
Exact Location Dombivli East

31)

Project Name Construction of Road in Kalyan Dombivali Municipal Corporation Area (Package 4)
Brief description and silent feature
  • Project Details
  • Administrative approval cost: 66.87cr
  • Contract cost: 66.87cr
  • Road work length: 6.8 km
  • Minor bridge: 02 no
  • Contract Details:
  • Name of Contractor: M/s.Eagle India Infra Ltd
  • Name of PMC: M/s. Composites combine technocrats Pvt Ltd
  • Project benefits:
  • Reduce traffic & travel time by 20 min. Better Kalyan east to Ulhasnagar city connectivity. It will facilitate smooth dispersal of traffic. Saving time and fuel.
Current Status Ongoing work (90%)
Exact Location Kalyan

32)

Project Name Construction of Cement Concrete Road works in Kalyan Dombivali Municipal Corporation Area. (Package 5).
Brief description and silent feature
  • Project Details
  • Administrative Approval Cost Rs. 332.05
  • Contract cost: 76.03 Cr.
  • Length of Roads- 4.890 Km.
  • No. of Lane- 2
  • Rigid Pavement + Flexible Pavement
  • SWD on Both sides with Footpath.
  • Cross duct for utilities crossing at every 200 mtr.
  • Contractor-M/s. R E Infra Pvt. Ltd.
  • PMC-M/s. Pentacle Consultant (I) Pvt Ltd.
  • Commencement of work- 22.12.2022
  • Project benefits:
  • Reduce Traffic and travel time by 10 to 20 min.
  • Saving in Fuel
  • Pot hole free roads
  • Less Maintenance.
Current Status Work in progress (87 %)
Exact Location Kalyan, Titwala & Ulhasnagar.

33)Design and Construction of Flyover at Kalyan Phata Junction on NH-4 (Old Mumbai Pune Highway.

MMRDA has taken up construction of Flyover at Shil Phata & Flyover at Kalyan Phata on NH-4 (Old Mumbai Pune Highway) under Extd. MUIP

Project Beneficiaries-:

After completion of these projects relief to traffic movement from Mumbra, Kalyan, Dombivali on large scale. Due to this project the distance between Kalyan Dombivli and Navi Mumbai curtails to 7 km which will reduce the travel time by 15.00 minutes. Presently heavy container traffic coming from JNPT to Gujarat bound and traffic coming from Kalyan-Dombivli towads Mumbai via Mahape causes heavy traffic jam towards Panvel side as well as at Kalyan side.

Project Key Components : -

  • Shil Phata Junction - a) Length Flyover –786.50 m b) Width of bridge – 12.00 m (3 +3 Lane)
  • Kalyan Phata Junction: a) Length Flyover –2394.04 m b) Width of bridge – 24.20 m (3 lane)

Project Cost & Completion Details

  • Administrative approval :- Rs. 410 Cr.
  • Project awarded to :- M/s. SMC Infrastructure Pvt. Ltd
  • Date of work order :- 09/04/2021
  • Contract Cost :- Rs.191.17 Cr.
  • Period of completion of project :- 30 Months
  • Revised date of completion of project :- 30/06/2025

Present Status:

The Contractor has submitted GAD of the integration of Metro line 14 with the Kalyan Phata Flyover, which is under scrutiny of Metro line- 14 DPR Consultant and T&C Division (MMRDA).

Shil Phata Junction :

  • Physical Progress: 99.20 %
  • Financial progress: 99.99 %
  • LHS side open for traffic dated 12/02/2024
  • RHS side open for traffic dated 03/05/2024

Kalyan Phata Junction :

  • Physical Progress: 20 %
  • Financial progress: 13.59 %

34)Construction of Kalyan Ring Road Segment – VIII from Runde Road to Goveli Road, Titwala.

Proposed work of Kalyan Ring Road (KRR) is a Kalyan Dombivali Municipal Corporation (KDMC) approved DP alignment, starts at Hedutane Village on Badlapur-Katai Road, Crosses Shil-Kalyan-Bhivandi Road near Bhopar village, Diva-Vasai Railway loop line & CRly line Kopar Railway station vicinity, connects Motagaon-Mankoli link road, crosses Diva-Vasai Railway line, follows further alignment parallel to Ulhas River, connects Shil-Kalyan-Bhivandi Road near Durgadi Bridge & ends at Titwala.

To & fro Traffic coming from Padgha-Nashik highway & Gujarat state and Pune & Karnataka state, currently plying through KDMC’s internal Road will get diverted through this KRR new link thereby expecting decongesting KDMC’s internal Road Construction work between Durgadi Chowk to Titwala (seg 4 to7-16.40km) has been completed in the length made available by KDMC for construction of road from Motagaon Bridge to Govindwadi Bypass (seg 3- 5.8) km) Contractor has been appointed.

During the joint meeting held on 03/10/2022, 06/07/2023 and 24/11/2023 with Hon. MP. Dr. Shrikant Shinde, it was decided to take up the Segment VIII work .

Administrative Approval

In the 134th meeting of the Authority held on 27/06/2014, administrative approval was given to the proposed cost of ₹ 3628.51 crores under resolution no. 1304 The said administrative approval covers the work of Kalyan Ring Road (Parts - 1 to 7) at a cost of ₹ 578 crores.

151st Authority Meeting held on 16/11/2021 under resolution no. 1573 at a cost of ₹ 661.36 crore was given administrative approval for Segment -3 (Mothagaon bridge to Gonvidwadi road).

MMRDA in its 156th Authority Meeting held on 05/03/2024 had accorded Administrative approval amounting to ₹ 39.86 Crore for segment-8.

  • Contractor: M/s N.A Construction pvt.ltd
  • Consultant : M/s TGP Projects
  • Cost of Work : Rs. 29.14Cr
  • Work order: 14/10/2024.
  • Completion Date: 18 Months Including Monsoon

Project Component /Beneficiaries:

  • Length: 1.096 Km width 30m
  • After work of Segment 8 is completed, the external bypass road will be used as a feeder road to Samuddhi Highway, Vadodara-Mumbai Highway and Kalyan-Ahmednagar Highway, Mumbai Nashik Highway for high speed traffic.

Present Status:

  • Physical progress- The survey work & demarcation is completed other work in Progress.
  • Financial Progress- Nil.

35)Construction of MTHL to Mumbai Pune Expressway

Project Details:

The MTHL Project is to provide a direct connection from Chirle to the Mumbai-Pune Highway. This is an alternative route to avoid traffic congestion on the JNPT to Panvel routes. Traffic coming and going from Pune-Goa will be handled without any hindrance via the Mumbai Port Project.

Project Features:

The proposed project includes a 6-lane bridge and the project is an important part of the wider MTHL project, which aims to connect Mumbai to Navi Mumbai more efficiently. The Chili and Palaspe sections are important points in the road network designed to connect the proposed Navi Mumbai International Airport (NMIA) with the existing infrastructure.

1. Chirle:

Chirle area is located near the upcoming airport and is being developed with a focus on providing smooth connectivity for both passengers and freight. The MTHL connector in this region includes construction of roads, bridges and interchanges, which will ensure efficient traffic flow between Navi Mumbai and other parts of Mumbai.

2. Palaspe:

Palaspe area is another important point in the connector, which connects MTHL to the Mumbai-Pune Expressway. This section is important for streamlining traffic movement between the two cities, reducing congestion and providing access to important destinations like the airport.

These connectors at Chirle and Palaspe together will significantly improve travel time, reduce congestion and increase economic opportunities in the Navi Mumbai region, which will play a key role in the development of the region.

Project Benefits:

The benefits of the Navi Mumbai MTHL Connector project include development of important road infrastructure to enhance connectivity between Mumbai and Navi Mumbai, focusing on areas like Chirle and Palaspe. Key components of the project include:

1. Bridges and Elevated Roads: Construction of elevated roads and bridges to connect key locations including the Mumbai Trans Harbour Link (MTHL) Mumbai-Pune Expressway and Navi Mumbai International Airport.

2. Interchanges: Development of interchanges for smooth traffic flow, reducing congestion and ensuring better access to surrounding areas.

3. Traffic Management: Measures to ease traffic and reduce congestion, reducing travel time between South Mumbai and Navi Mumbai from 90 minutes to approximately 30 minutes.

4. Environmental Matters: Efforts to reduce environmental impact, including eco-friendly construction methods and measures to protect local ecosystems.

5. Economic Growth: The project will support the development of Navi Mumbai, increase accessibility to the airport and increase trade and commerce in the region.

Overall, the project aims to improve regional connectivity, reduce traffic congestion, boost economic activities and provide critical infrastructure for future growth in the region.

Project Details:

The project is being implemented at a cost of Rs. 1420 crores have been given administrative approval. Also, the contract price is Rs. 1120.75 crores and the length is 7.35 km and the width is 11.5 + 11.5 m. (6 lanes).

Current status of the project:

Currently, the contractor was appointed on August 16, 2024 and the work order was issued. The geotechnical investigation work has been completed for the entire length of the project. The establishment of the casting yard and site office in the Chile section is in progress. The process of land acquisition for the service road in the Chile section is in progress. No Objection Certificate has been given for the construction of the project on October 25, 2024. Out of 176 locations, the work of foundation filling at 55 locations, installation of pillars at 35 locations and pillar caps at 8 locations has been completed. In addition, 125 out of 830 precast girders have been completed. The project is planned to be completed by February 2027.

36)Elevated Road from NH-04 (Old) To Katai Naka (Airoli Katai Naka Phase-III)

Project Feature:

  • Total length of the project: 6.71 km
  • Width: 45 m (3+3 lanes with service roads on both sides)
  • Length of Viaduct: 6158.719 m
  • Length of Ramps: 1579 m
  • Duration of Project Completion: 48 Months
  • Defect Liability Period: 24 Months
  • Project Cost: ₹1981.17 Crores
  • Date of Commencement: 11-10-2024
  • Proposed Date of Completion: 10-10-2028
  • Contractor: M/s. AFCONS Infrastructure Limited
  • Project Management Consultants: M/s. Smec International Pty. Ltd. in Association with Sui Generis Infratech Pvt. Ltd.

Present Status:

  • Land Acquisition Process is going on
  • DGPS Survey Completed
  • Topographic Survey is in progress
  • Geotechnical Investigation is in progress
  • Casting Yard Development is in progress
  • CRZ Clearance - Online application uploaded in Parivesh portal on 23-Jun-2025, MCZMA committee formed dated 07-Jul-2025, Agenda MCZMA published dated 08-Jul-2025, MCZMA committee meeting held on 14-Jul-2025 and it is agreed to send the proposal to MoEF Delhi
  • Forest Clearance - CA land letter submitted to MMRDA on 20-May-2025. Hon'ble AMC sir requested on 10-Jul-2025 to Hon'ble Collector sir of Hingoli for allocation of approximately 3.5 hectare CA land in village Kondhur, Taluka Kalamnuri, District Hingoli, Maharashtra

Project Major Features:

  • Up & Down ramp at Diva Shil Road, Katai Naka Junction and Badlapur Kalyan Road
  • The alignment crosses Mumbai-Ahmedabad bullet train alignment, Central Railway alignment & DFCC alignment

37)Design and construction of flyovers at Kalanagar junction,Bandra(E).

Project Feature:

  • The Kalanagar junction is getting congested day by day due to increased traffic from Worli Sea Link, Western Expressway, Dharavi side and BKC
  • The work pertains to connecting BKC to BWSL to and fro, and Dharavi to BWSL, which can help avoid the signals in between
  • The flyovers consist of 2 lanes having 82 spans in 3 arms (B, C, D), out of which 10 spans consist of steel girders. The clear height at junctions is 5.5 m
  • Kalanagar flyover will help to decongest the junction and will save about 10 minutes of travel time

Details of Project:

  1. Administrative Approval : Rs. 163.08 Crores
  2. Revised Cost of Project : Rs. 90.53 Crores
  3. Starting Date of Project : 02-01-2017
  4. Time Limit of Project : 30 Months
  5. Completion Date : 30-11-2021
  6. Proposed Structures :
    • Lengths of Bridge – Arm B (BWSL to BKC): 804 m, Arm C (BKC to BWSL): 653 m, Arm D (Dharavi to BWSL): 340 m
    • Width of Bridge – 9.9 m for each arm (including footpath)
    • Slab construction over the nallah

Present Status:

Arm C is opened on 21/02/2021 and Arm B is opened on 28/06/2021 for traffic.

  • Physical Progress – 99%
  • Financial Progress – 93.517%