PP15 RCC wall casting in progress
 
          PP39L-06 Pile Concrete Pouring in progress
 
          Friction slab casting in progress at P135 RHS
 
          PP39L-03 pile concrete pouring in progress
 
          P146-P147 RHS deck slab concrete pouring completed
 
          P187 LHS Abutment pile cap concrete pouring in progress
 
          P111 Pier final lift casting in progress
 
          PWS-C5-C6- Staircase Concrete Casting in progress
 
          P141-P142 RHS flyover deck slab casting completed
 
          CP6 CP7 Span RHS Parapet Stitch Casting in progress
 
          DHS C6 middle stitch concrete pouring in progress
 
          PP39L- 05 -pile Concrete Pouring in progress
 
          P142-P143 RHS Flyover deck slab concrete pouring completed.
 
          SBN C-12 RHS abutment wall casting in progress.
 
          P107 pier 1st lift concrete pouring work in progress.
 
          PWS C1 - C2 DG foundation slab concreting work in progress.