Mumbai Metro Line 4 (WADALA - KASARVADAVALI)

Mumbai Metro Line 4 (WADALA - KASARVADAVALI)

  • Metro Line 4 from Wadala to Kasarvadavali is 32.32 km. long elevated corridor with 32 stations.
  • It shall provide interconnectivity among the existing Eastern Express Roadway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), and the proposed Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli) & Metro Line 8 (Wadala to General Post Office).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • Dedicated Depots are planned in Owale land in up to an extent of 20 Ha. and in Godrej Land in up to 15.50 Ha. Area.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Project Features

 
Length 32.32 km
Stations 32 Nos.
  1. Bhakti Park Metro, 2. Wadala TT, 3. Anik Nagar Bus Depot, 4. Suman Nagar, 5. Siddharth Colony, 6. Amar Mahal Junction, 7. Garodia Nagar, 8. Pant Nagar, 9. Lakxmi Nagar, 10. Shreyes Cinema, 11. Godrej Company, 12. Vikhroli Metro, 13. Surya Nagar, 14. Gandhi Nagar, 15. Naval Housing, 16. Bhandup Mahapalika, 17. Bhandup Metro, 18. Shangrila, 19. Sonapur, 20. Mulund Fire Station, 21. Mulund Naka, 22. Thane Teen Haath Naka, 23. RTO Thane, 24. Mahapalika Marg, 25. Cadbury Junction, 26. Majiwada, 27. Kapurbawdi, 28. Manpada, 29. Tikuji-Ni-Wadi, 30. Dongari Pada, 31. Vijay Garden, 32. Kasarvadavali
Elevated / Underground Fully Elevated
Project base cost Rs. 14,549 Cr. (Incl. Taxes and Duties)
Ridership :  
2021 Daily Ridership - 8.70 Lakhs (PHPDT- 28107)
2031 Daily Ridership - 12.13 Lakhs (PHPDT- 33417)
Rolling Stock
Width : 3.20 m
Height : 3.90 m
Length : 21.84 m
Capacity System designed for 8 coach train : 2244 persons

 

Present Status

Updates as on 21st Oct 2019

 

 

Sr. No. Name of Work Status in %
1 Soil Investigation Works 83.0% of the soil investigation work for Pier foundation is completed.
2 Utility Works 70% completed
3 Piling Works 33% completed.
4 Pile Cap Works 18.60 % completed.
5 Pier Works 15.70 % completed.
6 Pier Cap Works

Pier Cap:6% Casting completed.

0.80% Erection completed.

7 U Girder Works U Girder: 2.33% casting completed.
 

Key Map

Photo Status

Piling activity

 

 

 

 

 

Pile cap excavation work

 

Pier Work