inner-banner

Metro Line - 4

Mumbai Metro Line 4 (WADALA - KASARVADAVALI)

  • Metro Line 4 from Wadala to Kasarvadavali is 32.32 km. long elevated corridor with 30 stations.
  • It shall provide interconnectivity among the existing Eastern Express Roadway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Length 32.32 km
Line Color Green Line
Stations 30 Nos.
  1. Bhakti Park Metro, 2. Wadala TT, 3. Anik Nagar Bus Depot, 4. Siddharth Colony, 5. Garodia Nagar, 6. Pant Nagar, 7. Laxmi Nagar, 8. Shreyes Cinema, 9. Godrej Company, 10.Vikhroli Metro, 11. Surya Nagar, 12. Gandhi Nagar, 13. Naval Housing, 14. BhandupMahapalika, 15. Bhandup Metro, 16. Shangrila, 17. Sonapur, 18. Mulund Fire Station, 19. Mulund Naka, 20. Thane Teen Haath Naka, 21. RTO Thane, 22. Mahapalika Marg, 23. Cadbury Junction, 24. Majiwada, 25. Kapurbawdi, 26. Manpada, 27. Tikuji-Ni-Wadi, 28. DongariPada, 29. Vijay Garden, 30. Kasarvadavali
Elevated / Underground Fully Elevated
Project base cost Rs. 14,549 Cr. (Incl. Taxes and Duties)
Ridership :
2031 Daily Ridership - 12.13 Lakhs (PHPDT- 33417)

Status as on 21.05.2023

Sr. No. Activity % Progress
1 Pile 89.2% completed.
2 Pile Cap 74.8% completed.
3 Pier(Viaduct+Station upto CL) 64.9% completed.
4 Anti Crash Barrier 56.3% completed.
5 Road Restoration 30.2% completed.
6 Pier Cap Casting 73.6% completed.
7 Pier Cap Erection 67.6% completed.
8 Stitch Concrete 66.7% completed.
9 Stressing 58.8% completed.
10 Bearing Pedestal 56.1% completed.
11 U-Girder Casting for Viaduct 73.1% completed.
12 U-Girder Erection for Viaduct 61.4% completed.
13 I-Girder Casting for Viaduct 27.1% completed.
14 I-Girder Erection for Viaduct 25.5% completed.
15 Deck Slab Over I Girder 25.9% completed.
16 U Girder Casting For Station 37.2% completed.
17 U Girder Erection For Station 31.3% completed.
18 Cast in Situ Pier Head for Station (Concourse level) 59.4% completed.
19 Concourse Level Pier Arm Casting 57.4% completed.
20 Concourse Level Pier Arm Erection 39.8% completed.
21 Platform Level Pier Arm Casting 57.5% completed.
22 Platform Level Pier Arm Erection 50.2% completed.
23 Station L Girder Casting 29.3% completed.
24 Station L Girder Erection 27.0% completed.
25 Station T Girder Casting 36.5% completed.
26 Station T Girder Erection 30.3% completed.
27 Platform Level RCC Beam Casting 29.2% completed.

 

Key Map-Metro Line 4