Mumbai Metro Line 4 (WADALA - KASARVADAVALI)

  • Metro Line 4 from Wadala to Kasarvadavali is 32.32 km. long elevated corridor with 30 stations.
  • It shall provide interconnectivity among the existing Eastern Express Roadway, Central Railway, Mono Rail, the ongoing Metro Line 2B (D N Nagar to Mandale), Metro Line 5 (Thane to Kalyan), Metro Line 6 (Swami Samarth Nagar to Vikhroli).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
Length 32.32 km
Line Color Green Line
Stations 30 Nos.
  1. Bhakti Park Metro, 2. Wadala TT, 3. Anik Nagar Bus Depot, 4. Siddharth Colony, 5. Garodia Nagar, 6. Pant Nagar, 7. Laxmi Nagar, 8. Shreyes Cinema, 9. Godrej Company, 10.Vikhroli Metro, 11. Surya Nagar, 12. Gandhi Nagar, 13. Naval Housing, 14. BhandupMahapalika, 15. Bhandup Metro, 16. Shangrila, 17. Sonapur, 18. Mulund Fire Station, 19. Mulund Naka, 20. Thane Teen Haath Naka, 21. RTO Thane, 22. Mahapalika Marg, 23. Cadbury Junction, 24. Majiwada, 25. Kapurbawdi, 26. Manpada, 27. Tikuji-Ni-Wadi, 28. DongariPada, 29. Vijay Garden, 30. Kasarvadavali
Elevated / Underground Fully Elevated
Project base cost Rs. 14,549 Cr. (Incl. Taxes and Duties)
Ridership :
2031 Daily Ridership - 12.13 Lakhs (PHPDT- 33417)

Status as on 10.02.2025

Sr. No. Activity % Progress
1 PIER (Viaduct+Station upto PL) 94% completed.
2 PIERCAP EREC 93% completed.
3 U GIRDER EREC 88% completed.
4 I GIRD EREC 65% completed.
5 DECK SLAB 59% completed.
6 L GIRD EREC 61% completed.
7 T GIRD EREC 68% completed.
8 RCC BEAM EREC 38% completed.
9 PORTAL BEAM EREC 16% completed.
10 PI GIRDER ERECTION 0% completed.