Metro Line - 5
Metro Line - 5 (Thane Bhiwandi Kalyan)
- Metro Line 5 from Thane to Bhiwandi to Kalyan is 24.90 km. long elevated corridor with 15 stations.
- It will provide interconnectivity among the ongoing Metro Line 4 (Wadala to Kasarvadavli) and the proposed Metro Line 12 (Kalyan to Taloja), and with the existing Central Railway.
- It will provide rail based access to the commercial, Govt. bodies and geographical landmarks in Thane, Bhiwandi and Kalayan.
- It will reduce the current travel time by anything between 50% and 75%
109
Length | 24.9 km (Elevated) |
Stations | 15 Nos. (All elevated) |
. | 1. Balkum Naka, 2. Kasheli, 3. Kalher, 4. Purna, 5. Anjurphata, 6. Dhamankar Naka, 7. Bhiwandi, 8. Gopal Nagar, 9. Temghar, 10. Rajnouli, 11. Gove Gaon, 12. Kon Gaon, 13. Lal Chowki, 14. Kalyan Station, 15. Kalyan APMC |
Elevated / Underground | Fully Elevated |
Project base cost | Rs. 8416.51 Cr. (including Taxes and Duties) |
Ridership : 2031 |
Daily Ridership –3.025 Lakhs (PHPDT- 26143) |
Rolling Stock |
Width : 3.20 m Height : 3.90 m Length : 21.84 m |
Capacity | System designed for 6 coach train : 1756 persons |
110
Present Status Updates as on 7thJune 2023
For Phase-I CA-28 (Thane-Bhiwandi)
Sr. No. | Name Of Work | Status in % |
---|---|---|
(Line 5)Construction Activity (Elevated) | ||
1 | Survey Work | 100% Completed. |
2 | Barricading board fixing | 82% completed |
3 | Soil investigation work | 100% completed. |
4 | Utility Identification Works | 89% completed. |
5 | Piling Works(Viaduct+Station) | 98% completed. |
6 | Pile cap Works(Viaduct+Station) | 97% completed. |
7 | Open Foundation | 100% completed. |
8 | Pier Works(Viaduct+Station) | 86% completed. |
9 | CIS Pier Cap | 100% completed. |
10 | Pier Cap Viaduct Erection | 84% completed. |
11 | U-Girder Viaduct Erection | 96% completed. |
12 | Spine Station Erection | 100% completed. |
13 | Wings Erection Station | 100% completed. |
14 | Pier arm Erection A1 Station | 100% completed. |
15 | Pier arm Erection A2 Station | 92% completed. |
16 | Erection of I-Girder viaduct) | 18% completed. |
17 | CIS I-Girder deck slab | 9% completed. |
Pre-Casting Works | ||
18 | Pier Cap | 86% completed. |
19 | U-Girder (Viaduct) | 100% completed. |
20 | U-Girder (Station) | 100% completed. |
21 | I-Girder Viaduct | 46% completed. |
22 | Spines | 100% completed. |
23 | Wings | 100% completed. |
24 | Pier Arm A1 | 100% completed. |
25 | Pier Arm A2 | 100% completed. |
26 | Platform L-Beam | 96% completed. |
27 | Parapet Wall | 70% completed. |
28 | Box Girder Segments | 100% completed. |
111