Mumbai Metro Line 4A (KASARVADAVALI - GAIMUKH)

  • Metro Line 4A from Kasarvadavali to Gaimukh is 2.7 km. long elevated corridor with 2 stations. It is the extension of Mumbai Metro Line-4 (Wadala – Ghatkopar – Mulund – Thane – Kasarvadavali corridor) at Kasarvadavali end.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.

Length

2.668 km (Fully Elevated)

Line Color

Green Line

Stations

2 Nos. (All Elevated)

Elevated / Underground

Elevated along Ghodbunder Road

Interchange Stations

  1. At Kasarvadavali (Metro Line 4)
  2. At Gaimukh (Metro Line 10)

Proposed Depot

Mogharpada (Provision made in Metro Line 4 Depot)

Project completion cost

₹ 949 Cr.

Daily Ridership (2031)

1.31 Lakhs (PHPDT - 30,708)

Present Status Updates as on 10th Feb 2025

Sr. No. Name Of Work Status in %
1 PIER (Viaduct+Station upto PL) 100% Completed.
2 PIERCAP EREC 94% completed
3 U GIRDER EREC 87% completed.
4 I GIRD EREC 64% completed.
5 DECK SLAB 60% completed.
6 PORTAL BEAM EREC 90% completed.
7 PI GIRDER ERECTION 100% completed.