Metro Line - 9 & 7A

Mumbai Metro Line 9 & 7A (i.e. Line 7 Extension)

  • Metro Line 9 is extension of Line 7 from Andheri to CSIA and Dahisar to Mira Bhayander and is 13.581 km long (11.386 km elevated and 2.195km underground) with 10 stations.
  • It shall provide interconnectivity among the existing Western Express Highway, Western Railway, ongoing Metro Line 2A (Dahisar to D N Nagar) and Metro Line 7(Andheri (E) to Dahisar (E)).
  • It shall provide rail based access to the commercial, Govt. bodies and geographical landmarks in Mumbai.
  • It shall reduce the current travel time by anything between 50% and 75% depending on road conditions.
 
Length 13.581 km
Stations 10 Nos.
 

Dahisar (E) to Mira-Bhayander ( All Elevated)

1. Dahisar, 2. Pandhurang Wadi, 3. Miragaon, 4. Kashigaon, 5. Sai Baba Nagar, 6. Meditiya Nagar, 7. Shahid Bhagat Singh Garden, 8. Subhash Chandra Bose Stadium

Andheri (E) to CSIA extension

1. Airport Colony (elevated) and 2. CSIA (underground)

Elevated / Underground 11.386 km elevated and 2.195 km underground
Project base cost Rs. 6607 Crore (including state taxes and 7.5% p.a escalation)
Ridership :
2021 Daily Ridership - 8.47 Lakh (PHPDT- 24585)
2031 Daily Ridership – 11.12 Lakh (PHPDT- 30389)
Rolling Stock

Width : 3.20 m

Height : 3.90 m

Length : 21.84 m

Capacity

8 coach train : 2352 persons

Updates as on 31st January 2025

Elevated Viaduct
Sr. No. Name of Work Status in %
1. Pier Cap Erection 98% Completed
2. U-Girder Erection 93% Completed
3. Portal Beam Erection 97% Completed
4. I-Girder Erection 100% Completed
5. Deck Slab Casting 93% Completed
6. Deck Slab Casting 93% Completed
8. Parapet Erection 85% Completed
Elevated Station
1. Concourse Pier Arm Erection 96% Completed
2. Platform Pier Arm Casting 100% Completed
3. Platform Pier Arm Erection 95% Completed
4. Portal Beam Erection (Dahisar Station) 100% Completed
5. U-Girder Erection 96% Completed
6. PI-Girder Erection 90% Completed
7. L-Girder Erection 97% Completed
8. T-Girder Erection 93% Completed
Flyover
1. Hammer Head 100% Completed
2. Abutment Pile 100% Completed
3. Abutment Pile Cap 100% Completed
4. Abutment Pier Cap 83% Completed
5. Dirt Wall 83% Completed
6. Flyover Pier Cap Casting 90% Completed
7. Flyover Pier Cap Erection 88% Completed
8. I-Girder Casting 92% Completed
9. I-Girder Erection 86% Completed
10. Deck Slab Casting 73% Completed
Line _7A
Sr. No. Name of Work Status in % Against Total Scope
Elevated Viaduct
1. U-Girder Erection 100% Completed
2. I-Girder Erection 100% Completed
3. Deck Slab Casting 100% Completed
Elevated Station
1. Portal Pier (Up to PL) 100% Completed
2. Pier Cap Erection 100% Completed
3. Portal Beam Casting at PL (Cast in Situ) 100% Completed
4. Tie Beam 100% Completed
5. U-Girder Erection 100% Completed
6. Casting of Extended Pier 100% Completed
7. Pi-Girder Casting 23% Completed
8. Precast Portal Beam Casting @CL 17% Completed
ELEVATED RAMP
1. Elevated Ramp 80% Completed
Tunnel
1. Tunnel Ring Segment Casting 99% Completed
2. Main Tunnel  
3. TBM-1 (Down Line) 92% Completed
4. TBM-2 (Up Line) 87% Completed
UG CSMIA Station
1. Base Slab (Sqm) 54% Completed
2. BS to CS wall (Sqm) 33% Completed
3. Column 1st Lift (BS to CS) 39% Completed
4. Column 2nd Lift (BS to CS) 33% Completed
5. Concourse Slab 20% Completed
6. CS to RS Wall 15% Completed
7. Column (CS to RS) 19% Completed
8. Roof slab 7% Completed