Launching of TBM components
P114 Pier 1st lift casting in progress.
SBSS-C08 Pier 1st Lift casting in progress.
CP104 Pile cap concrete pouring in progress
DHS EE1-C2 Pile concrete completed.
DHS C2 Hammer Head casting in progress.
P135 LHS Abutment Pile Cap casting in progress.
PP251L Pile Cap casting completed.
U Girder PP1-PP2 RHS concrete pouring completed.
F1 gantry footing concrete in progress.
F2 gantry foundation concrete completed.
P20 Pier casting in progress.
Shotcrete work in progress at zone D.
P15 Pier cap Erection completed.
P16 Pier protection concrete in progress.
Hon. Addl. Metropolitan Commissioner-II visit to Metro Line 9