CP-249-01 Pile concrete pouring in progress
PP10 portal middle stitch concrete pouring completed
P141-P142 LHS deck slab concrete pouring completed
PP100R-6 Pile casting in progress
DHS C6 PPC stitch concrete in progress
P151-P152RHS Flyover deck slab casting completed
PP15 RCC wall casting in progress
PP39L-06 Pile Concrete Pouring in progress
Friction slab casting in progress at P135 RHS
PP39L-03 pile concrete pouring in progress
P146-P147 RHS deck slab concrete pouring completed
P187 LHS Abutment pile cap concrete pouring in progress
P111 Pier final lift casting in progress
PWS-C5-C6- Staircase Concrete Casting in progress
P141-P142 RHS flyover deck slab casting completed
CP6 CP7 Span RHS Parapet Stitch Casting in progress