inner-banner

Present Status

Metro Line 6
Status as on 18.02.2025

Sr.No. Name of Work Status in %
1. Pile Cap Works 93.00 % completed.
2. Pier Works 89.00 % completed.
3. Pier Cap Works 91.00 % Erection completed.
4. Flyover Pier Cap 93.00 % Erection completed.
5. U Girder Works 86.00 % Erection completed.
6. Stations Works 73.60 % completed.
7. Station Entry-Exit Works 29.50 % completed.
Metro Line - 6
Show On Homepage
Off