Sr.No. | Name of Work | Status in % |
---|---|---|
1. | Pile Cap Works | 93.00 % completed. |
2. | Pier Works | 89.00 % completed. |
3. | Pier Cap Works | 91.00 % Erection completed. |
4. | Flyover Pier Cap | 93.00 % Erection completed. |
5. | U Girder Works | 86.00 % Erection completed. |
6. | Stations Works | 73.60 % completed. |
7. | Station Entry-Exit Works | 29.50 % completed. |